15837 W ROYAL OAK ROAD 91436

Certificate Information: 15837 W ROYAL OAK ROAD 91436

Application / Permit
21010-20000-05501
Plan Check / Job No.
B21VN14428
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD,15219 SQFT W/ ATTACHED 3 CAR GARAGE,833 SQFT AND COVERED PATIO,954 SQFT AND BASEMENT 5024 SQFT, (139'-6"x118-4") W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 4/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 PETER MOSESIAN
Corrections Issued 11/25/2021 PETER MOSESIAN
Quality Review Completed 12/3/2021 OMID HEDAYAT
Building Plans Picked Up 12/6/2021 APPLICANT
Applicant returned to address corrections 2/25/2022 PETER MOSESIAN
Plan Check Approved 4/26/2022 PETER MOSESIAN
Issued 4/26/2022 APPLICANT
CofO in Progress 2/23/2026 THOMAS FINNILA
Permit Finaled 5/22/2026 JOHN JANSON
CofO Issued 5/22/2026 JOHN JANSON
Permit Finaled 5/22/2026 JOHN JANSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/23/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/23/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/23/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/23/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/23/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/23/2021 CARLOS AGUILERA
Permit Cleared 11/23/2021 CARLOS AGUILERA
Sewer availability Cleared 11/23/2021 CARLOS AGUILERA
Trees in Parkway Cleared 12/15/2021 ADALBERTO VERA
Low Impact Development Cleared 1/24/2022 JONATAN VELASQUEZ
Hydrant and Access approval Cleared 2/8/2022 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 2/15/2022 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Markov,, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/28/2022 Approved DAVID SANDOVAL
Piling/Pier/Caisson 5/25/2022 Corrections Issued DAVID SANDOVAL
Piling/Pier/Caisson 6/6/2022 Approved ROBERT GOLD
PLUMBING-Rough 6/29/2022 Partial Approval VINCENT HANLEY
Underground Mechanical 6/29/2022 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 7/5/2022 Partial Approval VINCENT HANLEY
Green Building Rough 7/22/2022 Not Ready for Inspection VINCENT HANLEY
Reinforced Concrete Frame 7/22/2022 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 7/22/2022 Not Ready for Inspection VINCENT HANLEY
Deputy Shotcrete 7/27/2022 Conditional Approval MORRIS JACKSON
Reinforced Masonry Frame 7/27/2022 Partial Approval VINCENT HANLEY
Deputy Reinf. Masonry 8/5/2022 Conditional Approval JOHN JANSON
Green Building Rough 8/11/2022 Not Ready for Inspection VINCENT HANLEY
Reinforced Concrete Frame 8/11/2022 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 8/11/2022 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 8/23/2022 Partial Approval VINCENT HANLEY
Reinforced Concrete Frame 8/23/2022 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 9/1/2022 No Access for Inspection PETER FOLLING
Deputy Reinf. Concrete 9/8/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 9/9/2022 Approved VINCENT HANLEY
Green Building Rough 9/12/2022 Not Ready for Inspection VINCENT HANLEY
Reinforced Concrete Frame 9/12/2022 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 9/12/2022 Not Ready for Inspection VINCENT HANLEY
Deputy Shotcrete 9/14/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 9/22/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 9/28/2022 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 11/22/2022 Approved VINCENT HANLEY
Underground Mechanical 11/22/2022 Partial Approval VINCENT HANLEY
Deputy Shotcrete 12/2/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/22/2022 Partial Approval VINCENT HANLEY
Green Building Rough 12/22/2022 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 12/22/2022 Partial Approval VINCENT HANLEY
Reinforced Concrete Frame 12/22/2022 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 12/22/2022 Not Ready for Inspection VINCENT HANLEY
Deputy Reinf. Concrete 12/23/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 12/27/2022 Approved SEAN HAUPT
Deputy Reinf. Concrete 1/19/2023 Approved VINCENT HANLEY
Green Building Rough 1/19/2023 Not Ready for Inspection VINCENT HANLEY
Reinforced Concrete Frame 1/19/2023 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 1/19/2023 Not Ready for Inspection VINCENT HANLEY
Deputy Reinf. Concrete 1/20/2023 Approved VINCENT HANLEY
Sewer 2/3/2023 Approved VINCENT HANLEY
Piling/Pier/Caisson 2/10/2023 Corrections Issued VINCENT HANLEY
Deputy Reinf. Concrete 2/13/2023 Approved VINCENT HANLEY
Piling/Pier/Caisson 2/14/2023 Approved VINCENT HANLEY
Deputy Reinf. Concrete 2/15/2023 Approved VINCENT HANLEY
Deputy Other (see comments) 2/21/2023 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 2/22/2023 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 3/7/2023 Approved VINCENT HANLEY
Deputy Reinf. Concrete 3/9/2023 Approved VINCENT HANLEY
Masonry Wall/Backfill 3/9/2023 Partial Approval VINCENT HANLEY
Deputy Steel/Welding 3/20/2023 Approved VINCENT HANLEY
PLUMBING-Rough 3/20/2023 Partial Approval VINCENT HANLEY
Underground Mechanical 3/20/2023 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 3/24/2023 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 4/4/2023 Approved VINCENT HANLEY
Deputy Shotcrete 4/11/2023 Approved VINCENT HANLEY
Deputy Reinf. Concrete 4/17/2023 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 4/17/2023 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 4/18/2023 Partial Approval VINCENT HANLEY
Green Building Rough 4/18/2023 Not Ready for Inspection VINCENT HANLEY
Special/Order Compliance 4/18/2023 Partial Inspection MORRIS JACKSON
Verify Sprinkler Sign Off 4/18/2023 Not Ready for Inspection VINCENT HANLEY
Deputy Reinf. Concrete 4/19/2023 Approved VINCENT HANLEY
Deputy Steel/Welding 6/5/2023 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 6/7/2023 Partial Approval VINCENT HANLEY
Deputy Wood Construction 6/7/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Approval VINCENT HANLEY
Green Building Rough 6/7/2023 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Corrections Issued VINCENT HANLEY
Green Building Rough 7/24/2023 Not Ready for Inspection VINCENT HANLEY
Structural Steel Frame 7/24/2023 Corrections Issued VINCENT HANLEY
Verify Sprinkler Sign Off 7/24/2023 Not Ready for Inspection VINCENT HANLEY
Wood Frame 7/24/2023 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 9/21/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval VINCENT HANLEY
Green Building Rough 9/21/2023 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 9/21/2023 Not Ready for Inspection VINCENT HANLEY
Deputy Drilled-In Anchors 9/22/2023 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 11/3/2023 Approved SEAN WIRCH
Deputy Wood Construction 11/17/2023 Conditional Approval MORRIS JACKSON
BUILDING-Rough-Frame 11/21/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 11/21/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Approved VINCENT HANLEY
Green Building Rough 11/21/2023 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 11/21/2023 Approved VINCENT HANLEY
PLUMBING-Rough 11/21/2023 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 11/21/2023 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 12/12/2023 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 12/15/2023 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 1/10/2024 Corrections Issued VINCENT HANLEY
Green Building Rough 1/10/2024 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 1/10/2024 Not Ready for Inspection VINCENT HANLEY
Wood Frame 1/10/2024 Corrections Issued VINCENT HANLEY
Deputy Wood Construction 6/13/2024 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval MORRIS JACKSON
HVAC-Rough 7/30/2024 Approved MORRIS JACKSON
PLUMBING-Rough 7/30/2024 Approved MORRIS JACKSON
Deputy Wood Construction 7/31/2024 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 8/1/2024 Partial Inspection THOMAS FINNILA
ELECTRICAL-Rough 8/5/2024 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 8/6/2024 Approved THOMAS FINNILA
Shower Pan 8/29/2024 Approved ALEXANDER HANDY
Underground Mechanical 8/29/2024 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 9/24/2024 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 9/30/2024 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 10/7/2024 Corrections Issued THOMAS FINNILA
Green Building Rough 10/7/2024 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 10/7/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 10/10/2024 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 10/18/2024 Partial Approval THOMAS FINNILA
Drywall Nailing 10/28/2024 Partial Approval MORRIS JACKSON
Insulation 10/28/2024 Partial Approval MORRIS JACKSON
Interior/Exterior Lathing 10/28/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 11/1/2024 Approved THOMAS FINNILA
Drywall Nailing 11/7/2024 Approved MORRIS JACKSON
HVAC-Final 7/14/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 8/4/2025 Partial Inspection THOMAS FINNILA
ELECTRICAL-Final 8/7/2025 Not Ready for Inspection THOMAS FINNILA
Service/Power Release 9/29/2025 Approved THOMAS FINNILA
Rough-Elec/Plmb/HVAC 11/5/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 11/13/2025 Approved MORRIS JACKSON
PLUMBING-Final 11/13/2025 Approved MORRIS JACKSON
Smoke Detectors 11/13/2025 Not Ready for Inspection MORRIS JACKSON
HVAC-Final 11/20/2025 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 12/17/2025 Approved MORRIS JACKSON
Final 1/9/2026 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 1/9/2026 Approved SEAN WIRCH
Green Building Final 1/9/2026 Approved THOMAS FINNILA
Reinforced Concrete Frame 1/9/2026 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 1/9/2026 SGSOV Approved THOMAS FINNILA
Smoke Detectors 1/9/2026 Approved THOMAS FINNILA
Structural Steel Frame 1/9/2026 Approved SEAN WIRCH
Deputy Wood Construction 1/13/2026 Conditional Approval THOMAS FINNILA
Final 1/13/2026 Corrections Issued THOMAS FINNILA
Final 1/27/2026 Corrections Issued THOMAS FINNILA
Final 1/30/2026 Not Ready for Inspection THOMAS FINNILA
Final 2/23/2026 OK to Issue CofO THOMAS FINNILA