23602 W SPIRES ST 91304

Certificate Information: 23602 W SPIRES ST 91304

Application / Permit
21010-20000-05491
Plan Check / Job No.
B21VN14414
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 37' X 23' TWO STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (E), ALL WORK PER ENGINEERING ; “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 1/18/2022
Issuing Office
Current Status
Issued on 1/18/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/20/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 RARES BODEA
Corrections Issued 11/12/2021 RARES BODEA
Quality Review Completed 11/18/2021 STEVEN KIM
Building Plans Picked Up 11/19/2021 APPLICANT
Applicant returned to address corrections 1/11/2022 RARES BODEA
Plan Check Approved 1/18/2022 RARES BODEA
Issued 1/18/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/20/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/6/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/6/2021 CARLOS AGUILERA
Sewer availability Cleared 12/6/2021 CARLOS AGUILERA
GPI Written Notices Cleared 1/11/2022 RARES BODEA
Grading Pre-Inspection Cleared 1/11/2022 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/20/2022 Approved PETER FOLLING
Footing/Foundation/Slab 1/20/2022 Approved PETER FOLLING
PLUMBING-Rough 1/20/2022 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 2/3/2022 Partial Approval PETER FOLLING
Green Building Rough 2/3/2022 Not Ready for Inspection PETER FOLLING
Verify Sprinkler Sign Off 2/3/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 2/11/2022 Approved SEAN HAUPT
Green Building Rough 2/11/2022 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 2/11/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/3/2022 Approved DAVID SCANTLIN
ELECTRICAL-Rough 3/3/2022 Approved DAVID SCANTLIN
Green Building Rough 3/3/2022 Approved DAVID SCANTLIN
HVAC-Rough 3/3/2022 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/3/2022 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 3/3/2022 Approved DAVID SCANTLIN
Insulation 3/8/2022 Approved JESUS PINEDA
Drywall Nailing 3/17/2022 Approved RYAN SALAZAR
Shower Pan 3/17/2022 Approved RYAN SALAZAR
Final 12/1/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 12/1/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 12/1/2025 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 12/1/2025 Not Ready for Inspection JEFFREY HARTLINE