7236 N JAMIESON AVE 91335
Certificate Information: 7236 N JAMIESON AVE 91335
- Application / Permit
- 21010-20000-05490
- Plan Check / Job No.
- B21VN14413
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30' x 40' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). DESIGN PER WFPP.
- Permit Issued
- Issued on 10/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2021 | LUIS RINCON |
| Corrections Issued | 10/28/2021 | LUIS RINCON |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
| Plan Check Approved | 10/6/2022 | MIROOSH KHACHATOORIAN |
| Issued | 10/12/2022 | APPLICANT |
| CofO in Progress | 2/15/2024 | JEFFREY BULL |
| Permit Finaled | 3/14/2024 | JOHN JANSON |
| CofO Issued | 3/14/2024 | JOHN JANSON |
| Permit Finaled | 3/14/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/22/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 7/3/2022 | RUEL COLE |
| Low Impact Development | Cleared | 8/10/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/8/2022 | CARLOS AGUILERA |
| Hold | Cleared | 3/2/2023 | JEREMY CORONEL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/6/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 4/5/2023 | Partial Approval | JEFFREY BULL |
| Sewer | 4/5/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 4/12/2023 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Partial Approval | JEFFREY BULL |
| Insulation | 4/12/2023 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 4/20/2023 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Rough | 5/8/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 5/8/2023 | Partial Approval | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 5/8/2023 | Approved | DAVID SCANTLIN |
| Wood Frame | 5/8/2023 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 5/16/2023 | Approved | JEFFREY BULL |
| Special/Order Compliance | 5/16/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 9/8/2023 | Approved | JEFFREY BULL |
| Final | 9/8/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 9/8/2023 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 9/8/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 9/8/2023 | Not Required | JEFFREY BULL |
| Smoke Detectors | 9/8/2023 | Not Ready for Inspection | JEFFREY BULL |
| Verify Sprinkler Sign Off | 9/8/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 2/15/2024 | Approved | JEFFREY BULL |
| Final | 2/15/2024 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 2/15/2024 | Approved | JEFFREY BULL |
| HVAC-Final | 2/15/2024 | Approved | JEFFREY BULL |
| PLUMBING-Final | 2/15/2024 | Approved | JEFFREY BULL |
| Smoke Detectors | 2/15/2024 | Approved | JEFFREY BULL |