7834 N LINDLEY AVE 91335
Certificate Information: 7834 N LINDLEY AVE 91335
- Application / Permit
- 21010-20000-05484
- Plan Check / Job No.
- B21VN14381
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan 1. EXISTING GARAGE CONVERTED TO A.D.U PER GCS 65852.2(e)(1)(A). 2. NEW 8'-4" X 9'-4" BBQ WOOD TRELLIS PATIO COVER 3. NEW MINI SPLIT SYSTEM WITH HEAT PUMP 4. NEW TANKLESS WATER HEATER 5. NEW 100 AMP SERVICE PANEL FOR NEW ADU
- Permit Issued
- Issued on 1/3/2022
- Issuing Office
- Current Status
- CofO Issued on 1/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2021 | ZAW HAN |
| Corrections Issued | 10/28/2021 | ZAW HAN |
| Plan Check Approved | 11/17/2021 | ZAW HAN |
| Issued | 1/3/2022 | APPLICANT |
| CofO in Progress | 1/26/2023 | JEFFREY BULL |
| Permit Finaled | 1/27/2023 | JOHN JANSON |
| CofO Issued | 1/27/2023 | JOHN JANSON |
| Permit Finaled | 1/27/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2021 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 11/4/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2021 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/30/2022 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/30/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Approved | VINCENT HANLEY |
| Insulation | 4/4/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/26/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 4/26/2022 | Approved | JEFFREY PARD |
| HVAC-Rough | 4/26/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 4/26/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/11/2022 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/11/2022 | Partial Approval | VINCENT HANLEY |
| Sewer | 5/11/2022 | Approved | VINCENT HANLEY |
| Underground Mechanical | 5/11/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | DAVID SANDOVAL |
| Shower Pan | 5/27/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 6/3/2022 | No Access for Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/3/2022 | No Access for Inspection | MORRIS JACKSON |
| Drywall Nailing | 6/8/2022 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 6/8/2022 | Approved | DAVID SCANTLIN |
| Final | 1/6/2023 | Corrections Issued | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 1/6/2023 | Approved | JEFFREY BULL |
| Final | 1/19/2023 | OK to Issue CofO | JEFFREY BULL |
| Service/Power Release | 1/19/2023 | Approved | JEFFREY BULL |