1357 1/2 E 55TH ST 90011
Certificate Information: 1357 1/2 E 55TH ST 90011
- Application / Permit
- 21010-20000-05457
- Plan Check / Job No.
- B21VN14215
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 33'-3" x 38'-0" DET. ACCESSORY DWELLING UNIT (PER LAMC 12.22 A.33 (c)-(d)) W/ 2-CAR CARPORT AND STORAGE AREA BELOW
- Permit Issued
- Issued on 7/19/2022
- Issuing Office
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/11/2021 | SEAN SHAHMIRI |
| Corrections Issued | 11/16/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 11/29/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/2/2021 | APPLICANT |
| Plan Check Approved | 7/12/2022 | SEAN SHAHMIRI |
| Issued | 7/19/2022 | APPLICANT |
| CofO in Progress | 12/2/2023 | ALEJANDRO DE ARTOLA |
| CofO Issued | 12/14/2023 | DEROLD HAUFF |
| Permit Finaled | 12/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 1/11/2022 | ABEL CASILLAS |
| Construction near power lines | Cleared | 2/12/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 4/22/2022 | DWIGHT SANKEY |
| Low Impact Development | Cleared | 4/22/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/25/2022 | ABEL CASILLAS |
Contact Information
| Contractor | Ivy Green Construction; Lic. No.: 1014647-B | 14537 VENTURA BLVD SHERMAN OAKS, CA 91403 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16200 VENTURA BLVD SUITE 227 ENCINO, CA 91436 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/27/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/27/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/1/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/1/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/3/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/10/2022 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 8/26/2022 | Corrections Issued | RONALD MYRICK |
| Footing/Foundation/Slab | 8/26/2022 | Not Ready for Inspection | RONALD MYRICK |
| Special/Order Compliance | 8/26/2022 | Not Ready for Inspection | DEROLD HAUFF |
| Underground Mechanical | 8/26/2022 | Not Ready for Inspection | RONALD MYRICK |
| Excavation/Setback/Form/Re-Bar | 9/2/2022 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 9/2/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 9/2/2022 | Partial Approval | HORACE FULTZ |
| Deputy Reinf. Concrete | 9/6/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Corrections Issued | HORACE FULTZ |
| BUILDING-Rough-Frame | 1/18/2023 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 1/18/2023 | Corrections Issued | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 1/18/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 2/21/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 2/21/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 2/21/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 2/23/2023 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/1/2023 | Conditional Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2023 | Approved | HORACE FULTZ |
| Rough-Elec/Plmb/HVAC | 3/1/2023 | Conditional Approval | HORACE FULTZ |
| BUILDING-Rough-Frame | 4/12/2023 | Corrections Issued | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 4/12/2023 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 4/12/2023 | Approved | DONALD CRICHLOW |
| Underground Mechanical | 4/12/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 4/13/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 4/13/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 4/13/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 5/3/2023 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/30/2023 | Corrections Issued | ENRIQUE MIRELES |
| Shower Pan | 5/30/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/23/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/23/2023 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/3/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 9/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 9/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 9/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 9/25/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 9/25/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 10/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/30/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/30/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 10/30/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/30/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/30/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/1/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |