4914 N VARNA AVE 91423
Certificate Information: 4914 N VARNA AVE 91423
- Application / Permit
- 21010-20000-05455
- Plan Check / Job No.
- B21VN14203
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 65'-1" X 41'-4" IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND TRELLIS. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 2/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | COLIN LOREDO |
| Corrections Issued | 11/2/2021 | COLIN LOREDO |
| Quality Review Completed | 11/2/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| Applicant returned to address corrections | 11/30/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 4/6/2022 | COLIN LOREDO |
| Plan Check Approved | 4/6/2022 | COLIN LOREDO |
| Issued | 4/26/2022 | APPLICANT |
| CofO in Progress | 11/6/2023 | MISAEL ESPARZA |
| Permit Finaled | 2/9/2024 | RUBEN SALAS |
| CofO Issued | 2/9/2024 | RUBEN SALAS |
| Permit Finaled | 2/9/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 12/17/2021 | DAGOVERTO GUERRERO |
| ZI | Cleared | 1/14/2022 | MAYELA VILLA |
| Hydrant and Access approval | Cleared | 3/4/2022 | DWAYNE LAURENT |
| Low Impact Development | Cleared | 3/24/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/30/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/30/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/19/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/27/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/2/2022 | Partial Approval | MISAEL ESPARZA |
| Service/Power Release | 6/24/2022 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2022 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 8/23/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/31/2022 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 9/7/2022 | Partial Approval | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Corrections Issued | MISAEL ESPARZA |
| Gas Test | 9/9/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Pool Piping | 9/9/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 9/15/2022 | Approved | MISAEL ESPARZA |
| Sewer | 9/15/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/21/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 9/21/2022 | Approved | MISAEL ESPARZA |
| Sewer | 9/21/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/23/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/30/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/30/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 9/30/2022 | Corrections Issued | MISAEL ESPARZA |
| Pool Piping | 10/13/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/17/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/3/2022 | Conditional Approval | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 11/3/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 11/3/2022 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/14/2022 | Partial Approval | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 11/14/2022 | Approved | MISAEL ESPARZA |
| Insulation | 11/22/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 11/30/2022 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/20/2022 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 12/29/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/6/2023 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/18/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 2/17/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/4/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 5/4/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 5/4/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/10/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 5/10/2023 | Conditional Approval | THOMAS FINNILA |
| HVAC-Final | 5/17/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 5/17/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 5/23/2023 | Approved | JOHN COLEMAN |
| Final | 6/8/2023 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 6/8/2023 | Approved | JOHN COLEMAN |
| Green Building Final | 6/8/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 6/8/2023 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 6/8/2023 | Corrections Issued | JOHN COLEMAN |
| Smoke Detectors | 6/8/2023 | Approved | JOHN COLEMAN |
| Sewer | 7/28/2023 | Partial Inspection | MISAEL ESPARZA |
| Service/Power Release | 8/2/2023 | Approved | JUAN VALENZUELA |
| Final | 8/18/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 11/3/2023 | OK to Issue CofO | MISAEL ESPARZA |