4914 N VARNA AVE 91423

Certificate Information: 4914 N VARNA AVE 91423

Application / Permit
21010-20000-05455
Plan Check / Job No.
B21VN14203
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 65'-1" X 41'-4" IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND TRELLIS. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/26/2022
Issuing Office
Current Status
CofO Issued on 2/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 COLIN LOREDO
Corrections Issued 11/2/2021 COLIN LOREDO
Quality Review Completed 11/2/2021 OMID HEDAYAT
Building Plans Picked Up 11/2/2021 APPLICANT
Applicant returned to address corrections 11/30/2021 COLIN LOREDO
Applicant returned to address corrections 4/6/2022 COLIN LOREDO
Plan Check Approved 4/6/2022 COLIN LOREDO
Issued 4/26/2022 APPLICANT
CofO in Progress 11/6/2023 MISAEL ESPARZA
Permit Finaled 2/9/2024 RUBEN SALAS
CofO Issued 2/9/2024 RUBEN SALAS
Permit Finaled 2/9/2024 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 12/17/2021 DAGOVERTO GUERRERO
ZI Cleared 1/14/2022 MAYELA VILLA
Hydrant and Access approval Cleared 3/4/2022 DWAYNE LAURENT
Low Impact Development Cleared 3/24/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/30/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/30/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/5/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/19/2022 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 5/27/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/2/2022 Partial Approval MISAEL ESPARZA
Service/Power Release 6/24/2022 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 8/23/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/31/2022 Approved MISAEL ESPARZA
Deputy Wood Construction 9/7/2022 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Corrections Issued MISAEL ESPARZA
Gas Test 9/9/2022 Not Ready for Inspection MISAEL ESPARZA
Pool Piping 9/9/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 9/15/2022 Approved MISAEL ESPARZA
Sewer 9/15/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 9/21/2022 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 9/21/2022 Approved MISAEL ESPARZA
Sewer 9/21/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 9/23/2022 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 9/30/2022 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 9/30/2022 Corrections Issued MISAEL ESPARZA
HVAC-Rough 9/30/2022 Corrections Issued MISAEL ESPARZA
Pool Piping 10/13/2022 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/17/2022 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 11/3/2022 Conditional Approval MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 11/3/2022 Approved MISAEL ESPARZA
Wood Frame 11/3/2022 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 11/14/2022 Partial Approval MISAEL ESPARZA
Verify Sprinkler Sign Off 11/14/2022 Approved MISAEL ESPARZA
Insulation 11/22/2022 Approved MISAEL ESPARZA
Drywall Nailing 11/30/2022 Approved MISAEL ESPARZA
Shower Pan 12/20/2022 Corrections Issued MISAEL ESPARZA
Shower Pan 12/29/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 1/6/2023 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 1/18/2023 Approved MISAEL ESPARZA
Green Building Rough 2/17/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 5/4/2023 Corrections Issued MISAEL ESPARZA
HVAC-Final 5/4/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 5/4/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 5/10/2023 Approved THOMAS FINNILA
PLUMBING-Final 5/10/2023 Conditional Approval THOMAS FINNILA
HVAC-Final 5/17/2023 Approved JUAN VALENZUELA
PLUMBING-Final 5/17/2023 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 5/23/2023 Approved JOHN COLEMAN
Final 6/8/2023 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 6/8/2023 Approved JOHN COLEMAN
Green Building Final 6/8/2023 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 6/8/2023 SGSOV Approved JOHN COLEMAN
Service/Power Release 6/8/2023 Corrections Issued JOHN COLEMAN
Smoke Detectors 6/8/2023 Approved JOHN COLEMAN
Sewer 7/28/2023 Partial Inspection MISAEL ESPARZA
Service/Power Release 8/2/2023 Approved JUAN VALENZUELA
Final 8/18/2023 Corrections Issued MISAEL ESPARZA
Final 11/3/2023 OK to Issue CofO MISAEL ESPARZA