5755 N BUCKNELL AVE 91607
Certificate Information: 5755 N BUCKNELL AVE 91607
- Application / Permit
- 21010-20000-05454
- Plan Check / Job No.
- B21VN14188
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED (47'-0"x49'-6"), 1200 SQFT 1 STORY ADU- W/ATTACHED OPEN TRELLIS (363 SQFT) AND FRONT COVERED PORCH (69 SQFT) PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 5/23/2022
- Issuing Office
- Current Status
- CofO Issued on 4/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | PETER MOSESIAN |
| Corrections Issued | 11/6/2021 | PETER MOSESIAN |
| Quality Review Completed | 11/10/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/24/2021 | APPLICANT |
| Plan Check Approved | 5/12/2022 | PETER MOSESIAN |
| Issued | 5/23/2022 | APPLICANT |
| CofO in Progress | 4/18/2023 | JOHN HAYES |
| Permit Finaled | 4/27/2023 | MICHAEL SMITH |
| CofO Issued | 4/27/2023 | MICHAEL SMITH |
| Permit Finaled | 4/27/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/4/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 1/4/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 1/4/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/12/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 4/1/2022 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 4/22/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 5/3/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/4/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/28/2022 | Partial Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 7/11/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 7/18/2022 | Partial Approval | MISAEL ESPARZA |
| Piling/Pier/Caisson | 7/22/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Partial Approval | JOHN HAYES |
| Gas Test | 8/30/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/30/2022 | SGSOV Not Ready | JOHN HAYES |
| Underground Mechanical | 8/30/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 10/3/2022 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 10/5/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 10/28/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 10/28/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 10/28/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 10/28/2022 | Not Ready for Inspection | JOHN HAYES |
| Deputy Wood Construction | 11/2/2022 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 11/3/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Approved | JOHN HAYES |
| Green Building Rough | 11/3/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 11/3/2022 | Approved | JOHN HAYES |
| MERV13>=Rough | 11/3/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 11/3/2022 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 11/3/2022 | Approved | JOHN HAYES |
| Insulation | 11/23/2022 | Approved | JORDAN KUTZLY |
| Interior/Exterior Lathing | 11/23/2022 | Approved | JORDAN KUTZLY |
| Interior/Exterior Lathing | 12/2/2022 | Approved | JOHN HAYES |
| Shower Pan | 12/2/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 12/12/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 3/23/2023 | Approved | JENNIFER RABUCHIN |
| Final | 3/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 3/23/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/23/2023 | Approved | JENNIFER RABUCHIN |
| Final | 3/29/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 3/29/2023 | Approved | JOHN HAYES |
| Green Building Final | 3/29/2023 | Approved | JOHN HAYES |
| MERV13>=Final | 3/29/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/29/2023 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 3/29/2023 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 3/29/2023 | Approved | JOHN HAYES |
| Final | 4/13/2023 | No Access for Inspection | ROBERT GOLD |
| Service/Power Release | 4/13/2023 | No Access for Inspection | ROBERT GOLD |
| Final | 4/18/2023 | OK to Issue CofO | JOHN HAYES |
| Service/Power Release | 4/18/2023 | Approved | JOHN HAYES |