5755 N BUCKNELL AVE 91607

Certificate Information: 5755 N BUCKNELL AVE 91607

Application / Permit
21010-20000-05454
Plan Check / Job No.
B21VN14188
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED (47'-0"x49'-6"), 1200 SQFT 1 STORY ADU- W/ATTACHED OPEN TRELLIS (363 SQFT) AND FRONT COVERED PORCH (69 SQFT) PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 5/23/2022
Issuing Office
Current Status
CofO Issued on 4/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 PETER MOSESIAN
Corrections Issued 11/6/2021 PETER MOSESIAN
Quality Review Completed 11/10/2021 OMID HEDAYAT
Building Plans Picked Up 11/24/2021 APPLICANT
Plan Check Approved 5/12/2022 PETER MOSESIAN
Issued 5/23/2022 APPLICANT
CofO in Progress 4/18/2023 JOHN HAYES
Permit Finaled 4/27/2023 MICHAEL SMITH
CofO Issued 4/27/2023 MICHAEL SMITH
Permit Finaled 4/27/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/4/2022 CARLOS AGUILERA
Miscellaneous Cleared 1/4/2022 CARLOS AGUILERA
Miscellaneous Cleared 1/4/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/12/2022 CARLOS AGUILERA
Sewer availability Cleared 1/12/2022 CARLOS AGUILERA
Construction near power lines Cleared 4/1/2022 WALTER RAMIREZ
Hydrant and Access approval Cleared 4/22/2022 KURT CORRAL
Low Impact Development Cleared 5/3/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/4/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/28/2022 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 7/11/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 7/18/2022 Partial Approval MISAEL ESPARZA
Piling/Pier/Caisson 7/22/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Partial Approval JOHN HAYES
Gas Test 8/30/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Not Ready JOHN HAYES
Underground Mechanical 8/30/2022 Not Ready for Inspection JOHN HAYES
Underground Mechanical 10/3/2022 Corrections Issued JOHN HAYES
Underground Mechanical 10/5/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 10/28/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 10/28/2022 Not Ready for Inspection JOHN HAYES
HVAC-Rough 10/28/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 10/28/2022 Not Ready for Inspection JOHN HAYES
Deputy Wood Construction 11/2/2022 Conditional Approval MICHAEL SMITH
BUILDING-Rough-Frame 11/3/2022 Approved JOHN HAYES
ELECTRICAL-Rough 11/3/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Approved JOHN HAYES
Green Building Rough 11/3/2022 Approved JOHN HAYES
HVAC-Rough 11/3/2022 Approved JOHN HAYES
MERV13>=Rough 11/3/2022 Approved JOHN HAYES
PLUMBING-Rough 11/3/2022 Approved JOHN HAYES
Verify Sprinkler Sign Off 11/3/2022 Approved JOHN HAYES
Insulation 11/23/2022 Approved JORDAN KUTZLY
Interior/Exterior Lathing 11/23/2022 Approved JORDAN KUTZLY
Interior/Exterior Lathing 12/2/2022 Approved JOHN HAYES
Shower Pan 12/2/2022 Approved JOHN HAYES
Drywall Nailing 12/12/2022 Approved DAVID ANDERSON
ELECTRICAL-Final 3/23/2023 Approved JENNIFER RABUCHIN
Final 3/23/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 3/23/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/23/2023 Approved JENNIFER RABUCHIN
Final 3/29/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/29/2023 Approved JOHN HAYES
Green Building Final 3/29/2023 Approved JOHN HAYES
MERV13>=Final 3/29/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Approved JOHN HAYES
Service/Power Release 3/29/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 3/29/2023 Approved JOHN HAYES
Final 4/13/2023 No Access for Inspection ROBERT GOLD
Service/Power Release 4/13/2023 No Access for Inspection ROBERT GOLD
Final 4/18/2023 OK to Issue CofO JOHN HAYES
Service/Power Release 4/18/2023 Approved JOHN HAYES