4740 N BECK AVE 91602
Certificate Information: 4740 N BECK AVE 91602
- Application / Permit
- 21010-20000-05440
- Plan Check / Job No.
- B21VN14113
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (N) GARAGE TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2021 | DANIEL YIP |
| Corrections Issued | 10/20/2021 | DANIEL YIP |
| Applicant returned to address corrections | 10/29/2021 | DANIEL YIP |
| Applicant returned to address corrections | 11/9/2021 | DANIEL YIP |
| Applicant returned to address corrections | 12/2/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 12/14/2021 | DANIEL YIP |
| Issued | 12/22/2021 | APPLICANT |
| CofO in Progress | 8/15/2022 | DAVID MATSON |
| CofO in Progress | 8/15/2022 | DAVID MATSON |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
| CofO Issued | 8/27/2022 | MICHAEL SMITH |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/27/2021 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 11/30/2021 | ERIN NASH |
Contact Information
| Contractor | Ferguson Construction And Fine Cabinetry; Lic. No.: 787034-B | 6300 AGNES AVENUE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/15/2022 | Conditional Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 2/18/2022 | Approved | CALEB MEISTER |
| Footing/Foundation/Slab | 2/22/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/25/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/4/2022 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/7/2022 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 3/22/2022 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 3/29/2022 | Partial Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 4/7/2022 | Conditional Approval | MICHAEL TEMPLE |
| Wood Frame | 4/11/2022 | Partial Approval | THOMAS FINNILA |
| Insulation | 4/18/2022 | Corrections Issued | CALEB MEISTER |
| Drywall Nailing | 4/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Special/Order Compliance | 5/13/2022 | Approved | THOMAS FINNILA |
| Final | 7/6/2022 | Corrections Issued | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 7/6/2022 | Approved | JACK KARGODORIAN |
| Wood Frame | 7/6/2022 | Approved | JACK KARGODORIAN |
| Final | 7/20/2022 | Not Ready for Inspection | DAVID MATSON |
| Final | 7/22/2022 | Corrections Issued | DAVID MATSON |
| Final | 8/4/2022 | Corrections Issued | THOMAS FINNILA |
| Final | 8/11/2022 | OK to Issue CofO | DAVID MATSON |