20101 W GALWAY LANE 91326

Certificate Information: 20101 W GALWAY LANE 91326

Application / Permit
21010-20000-05436
Plan Check / Job No.
B21VN14107
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY SFD WITH ATTACHED THREE CAR GARAGE_STANDARD PLAN#652_ PLAN 2BR_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 4/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 11/11/2021 DAWN MC NULTY
Corrections Issued 11/17/2021 DAWN MC NULTY
Quality Review Completed 11/18/2021 STEVEN KIM
Applicant returned to address corrections 3/28/2023 DAWN MC NULTY
Plan Check Approved 3/30/2023 DAWN MC NULTY
Issued 4/13/2023 APPLICANT
CofO in Progress 5/1/2024 JEFFREY PARD
Permit Finaled 5/2/2024 JOHN JANSON
CofO Issued 5/2/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/9/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/9/2022 LEE GUILBEAUX
Permit Cleared 5/9/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/9/2022 DAWN MC NULTY
Roof/Waste drainage to street Cleared 5/9/2022 LEE GUILBEAUX
Sewer availability Cleared 5/9/2022 LEE GUILBEAUX
"T" removal Cleared 5/10/2022 DANG NGUYEN
CPC Cleared 5/10/2022 DANG NGUYEN
Frnt yard landscape/Water mgmt Cleared 5/10/2022 DANG NGUYEN
Miscellaneous Cleared 5/10/2022 DANG NGUYEN
Miscellaneous Cleared 5/10/2022 DANG NGUYEN
Miscellaneous Cleared 5/10/2022 DANG NGUYEN
Private street Cleared 5/10/2022 DANG NGUYEN
Specific Plan Cleared 5/10/2022 DANG NGUYEN
Tract Map conditions Cleared 5/10/2022 DANG NGUYEN
ZA Case Cleared 5/10/2022 DANG NGUYEN
ZA Case Cleared 5/10/2022 DANG NGUYEN
Low Impact Development Cleared 5/13/2022 AMMAR ELTAWIL
Hydrant and Access approval Cleared 5/20/2022 KURT CORRAL

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Braatz,, Tara Elizabeth; Lic. No.: C79028 24855 CALLE CARMEL      LAGUNA HILLS, CA 92653
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/14/2023 Partial Approval HENRY KIM
Footing/Foundation/Slab 8/24/2023 Approved JEFFREY PARD
Deputy Pre-Stress Concrete 9/7/2023 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Approved JEFFREY PARD
Sewer 11/7/2023 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Approved JEFFREY PARD
Underground Mechanical 11/22/2023 Not Ready for Inspection JEFFREY PARD
Underground Mechanical 11/29/2023 Approved JEFFREY PARD
Deputy Drilled-In Anchors 12/12/2023 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Approved JEFFREY PARD
ELECTRICAL-Rough 1/16/2024 Approved JEFFREY PARD
HVAC-Rough 1/16/2024 Approved JEFFREY PARD
PLUMBING-Rough 1/16/2024 Approved JEFFREY PARD
Shower Pan 1/16/2024 Not Ready for Inspection JEFFREY PARD
Shower Pan 1/19/2024 Not Ready for Inspection JEFFREY PARD
Shower Pan 1/22/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 1/25/2024 Approved JEFFREY PARD
Green Building Rough 1/25/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 1/25/2024 Approved JEFFREY PARD
Verify Sprinkler Sign Off 1/25/2024 Approved JEFFREY PARD
Drywall Nailing 2/6/2024 Approved JEFFREY PARD
Gas Test 3/15/2024 Approved HENRY KIM
Service/Power Release 3/15/2024 Not Ready for Inspection HENRY KIM
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Approved JEFFREY PARD
Service/Power Release 3/21/2024 No Access for Inspection JEFFREY PARD
Service/Power Release 3/26/2024 Approved JEFFREY PARD
ELECTRICAL-Final 4/30/2024 Approved JEFFREY PARD
Final 4/30/2024 OK to Issue CofO JEFFREY PARD
Green Building Final 4/30/2024 Approved JEFFREY PARD
HVAC-Final 4/30/2024 Approved JEFFREY PARD
PLUMBING-Final 4/30/2024 Approved JEFFREY PARD
Smoke Detectors 4/30/2024 Approved JEFFREY PARD