10429 W JIMENEZ ST 91342

Certificate Information: 10429 W JIMENEZ ST 91342

Application / Permit
21010-20000-05377
Plan Check / Job No.
B21VN13972
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY 40' X 30' ACCESSORY DWELLING UNIT LAMC 12.22 A.33(c) AND (d) WITH ATTACHED 6' X 6' 1/2 BATHROOM WITH EXTERIOR ACCESS ONLY. "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
Permit Issued
Issued on 3/26/2022
Issuing Office
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 GURUNATH NESARAJAH
Corrections Issued 11/6/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 3/11/2022 GURUNATH NESARAJAH
Plan Check Approved 3/26/2022 GURUNATH NESARAJAH
Issued 3/26/2022 APPLICANT
Building Plans Picked Up 3/30/2022 APPLICANT
CofO in Progress 11/30/2022 WILLIAM WREN
CofO Issued 12/10/2022 MICHAEL SMITH
Permit Finaled 12/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/10/2021 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 1/11/2022 AMIR KASHFI
Sewer availability Cleared 1/11/2022 AMIR KASHFI
Specific Plan Cleared 1/12/2022 PEGGY MALONE-BROWN
Hydrant and Access approval Cleared 2/14/2022 DWAYNE LAURENT
Construction near power lines Cleared 3/1/2022 TINA MIRANDA
Roof/Waste drainage to street Cleared 3/3/2022 AMIR KASHFI
Grading Pre-Inspection Cleared 3/13/2022 GURUNATH NESARAJAH
Address approval Cleared 3/15/2022 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/22/2022 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 4/26/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 7/8/2022 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 7/8/2022 Approved MATTHEW NELSON
Green Building Rough 7/8/2022 Approved MATTHEW NELSON
HVAC-Rough 7/8/2022 Not Ready for Inspection MATTHEW NELSON
MERV13>=Rough 7/8/2022 Approved MATTHEW NELSON
PLUMBING-Rough 7/8/2022 Approved MATTHEW NELSON
Rough-Elec/Plmb/HVAC 7/8/2022 Partial Approval MATTHEW NELSON
Verify Sprinkler Sign Off 7/8/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/15/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/19/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 7/19/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 7/19/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/19/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 7/29/2022 Approved MATTHEW NELSON
Shower Pan 7/29/2022 Approved MATTHEW NELSON
Drywall Nailing 8/5/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/9/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 11/9/2022 Approved JENNIFER RABUCHIN
Final 11/9/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/9/2022 Approved JENNIFER RABUCHIN
HVAC-Final 11/9/2022 Approved JENNIFER RABUCHIN
MERV13>=Final 11/9/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/9/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 11/9/2022 Approved JENNIFER RABUCHIN
Smoke Detectors 11/9/2022 Approved JENNIFER RABUCHIN
Final 11/29/2022 OK to Issue CofO WILLIAM WREN