13463 W HERRON ST 91342
Certificate Information: 13463 W HERRON ST 91342
- Application / Permit
- 21010-20000-05374
- Plan Check / Job No.
- B21VN13964
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 20' X 20' DETACHED TWO CAR GARAGE. ALL WORK PER WFPP.
- Permit Issued
- Issued on 11/5/2021
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | PARISA ZAHABI |
| Corrections Issued | 10/14/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 10/27/2021 | PARISA ZAHABI |
| Plan Check Approved | 11/4/2021 | PARISA ZAHABI |
| Issued | 11/5/2021 | APPLICANT |
| Building Plans Picked Up | 11/10/2021 | APPLICANT |
| CofO in Progress | 9/27/2022 | ARAM AVEDISIAN |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
| CofO Issued | 10/15/2022 | MICHAEL SMITH |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 10/15/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/12/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 6/13/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 6/13/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 6/13/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 6/13/2022 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 6/13/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 6/21/2022 | Approved | ARAM AVEDISIAN |
| Gas Test | 6/21/2022 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/21/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/21/2022 | Approved | ARAM AVEDISIAN |
| Wood Frame | 6/21/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 6/30/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/28/2022 | Approved | ROBERT GOLD |
| Final | 7/28/2022 | Corrections Issued | ROBERT GOLD |
| Footing/Foundation/Slab | 7/28/2022 | Approved | ROBERT GOLD |
| Green Building Final | 7/28/2022 | Not Ready for Inspection | ROBERT GOLD |
| Green Building Rough | 7/28/2022 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Not Ready | ROBERT GOLD |
| Service/Power Release | 7/28/2022 | Not Ready for Inspection | ROBERT GOLD |
| Smoke Detectors | 7/28/2022 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 8/3/2022 | Approved | ROBERT GOLD |
| Final | 8/3/2022 | Partial Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Approved | ROBERT GOLD |
| Green Building Final | 8/3/2022 | Approved | ROBERT GOLD |
| HVAC-Final | 8/3/2022 | Not Ready for Inspection | ROBERT GOLD |
| PLUMBING-Final | 8/3/2022 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Approved | ROBERT GOLD |
| Service/Power Release | 8/3/2022 | Not Ready for Inspection | ROBERT GOLD |
| Final | 9/27/2022 | OK to Issue CofO | ARAM AVEDISIAN |