17200 W LASSEN ST 91345
Certificate Information: 17200 W LASSEN ST 91345
- Application / Permit
- 21010-20000-05365
- Plan Check / Job No.
- B21VN13942
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED DETACHED 1 STORY ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Current Status
- CofO Issued on 10/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 12/2/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/10/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/28/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 6/13/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/15/2022 | HERNAN ARREOLA |
| Plan Check Approved | 8/15/2022 | HERNAN ARREOLA |
| No Progress | 8/15/2022 | HERNAN ARREOLA |
| Plan Check Approved | 9/21/2022 | CRYSTEL MAALOUF |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 8/13/2024 | JAVIER RAMOS JR |
| No Progress | 9/5/2024 | ROBERT GOLD |
| CofO in Progress | 9/5/2024 | ROBERT GOLD |
| Permit Finaled | 10/12/2024 | DANIEL ORRANTE |
| CofO Issued | 10/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/31/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 3/16/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/18/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 4/1/2022 | KIRK LINKLATER |
| Permit | Cleared | 5/2/2022 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 8/10/2022 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/16/2022 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 11/28/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 11/28/2022 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/29/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/22/2023 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/29/2023 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/29/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 3/29/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/29/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 4/19/2023 | Corrections Issued | JOHN COLEMAN |
| Interior/Exterior Lathing | 4/19/2023 | Partial Approval | JOHN COLEMAN |
| Shower Pan | 4/19/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/8/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 5/8/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/8/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/8/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/8/2023 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 5/8/2023 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 5/8/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 7/21/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 7/21/2023 | Corrections Issued | JAVIER RAMOS JR |
| Drywall Nailing | 1/8/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/8/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 1/8/2024 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 1/8/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 1/8/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 1/8/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/8/2024 | SGSOV Not Ready | JAVIER RAMOS JR |
| Service/Power Release | 1/8/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 1/8/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 1/8/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/13/2024 | Approved | JAVIER RAMOS JR |
| Final | 2/13/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 2/13/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/13/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Not Ready | JAVIER RAMOS JR |
| Service/Power Release | 2/13/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 2/13/2024 | Approved | JAVIER RAMOS JR |
| Final | 6/24/2024 | Partial Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Not Ready | JAVIER RAMOS JR |
| Service/Power Release | 6/24/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 8/13/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 8/13/2024 | Approved | JAVIER RAMOS JR |