17200 W LASSEN ST 91345

Certificate Information: 17200 W LASSEN ST 91345

Application / Permit
21010-20000-05365
Plan Check / Job No.
B21VN13942
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED DETACHED 1 STORY ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 9/21/2022
Issuing Office
Current Status
CofO Issued on 10/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 CRYSTEL MAALOUF
Corrections Issued 12/2/2021 CRYSTEL MAALOUF
Quality Review Completed 12/10/2021 HERNAN ARREOLA
Applicant returned to address corrections 4/28/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 6/13/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 8/15/2022 HERNAN ARREOLA
Plan Check Approved 8/15/2022 HERNAN ARREOLA
No Progress 8/15/2022 HERNAN ARREOLA
Plan Check Approved 9/21/2022 CRYSTEL MAALOUF
Issued 9/21/2022 APPLICANT
CofO in Progress 8/13/2024 JAVIER RAMOS JR
No Progress 9/5/2024 ROBERT GOLD
CofO in Progress 9/5/2024 ROBERT GOLD
Permit Finaled 10/12/2024 DANIEL ORRANTE
CofO Issued 10/12/2024 DANIEL ORRANTE
Permit Finaled 10/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/27/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/31/2022 CARLOS AGUILERA
Sewer availability Cleared 1/31/2022 CARLOS AGUILERA
Low Impact Development Cleared 3/16/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 3/18/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 4/1/2022 KIRK LINKLATER
Permit Cleared 5/2/2022 CARLOS AGUILERA
GPI Written Notices Cleared 8/10/2022 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/16/2022 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 11/28/2022 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 11/28/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 12/29/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 3/22/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 3/29/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 3/29/2023 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval JAVIER RAMOS JR
HVAC-Rough 3/29/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 3/29/2023 Approved JAVIER RAMOS JR
Insulation 4/19/2023 Corrections Issued JOHN COLEMAN
Interior/Exterior Lathing 4/19/2023 Partial Approval JOHN COLEMAN
Shower Pan 4/19/2023 Approved JOHN COLEMAN
BUILDING-Rough-Frame 5/8/2023 Approved JAVIER RAMOS JR
Drywall Nailing 5/8/2023 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 5/8/2023 Approved JAVIER RAMOS JR
Green Building Rough 5/8/2023 Approved JAVIER RAMOS JR
HVAC-Rough 5/8/2023 Corrections Issued JAVIER RAMOS JR
Insulation 5/8/2023 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/8/2023 Approved JAVIER RAMOS JR
Sewer 7/21/2023 Approved JAVIER RAMOS JR
Underground Mechanical 7/21/2023 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 1/8/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 1/8/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 1/8/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Final 1/8/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 1/8/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 1/8/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/8/2024 SGSOV Not Ready JAVIER RAMOS JR
Service/Power Release 1/8/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 1/8/2024 Approved JAVIER RAMOS JR
Underground Mechanical 1/8/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Final 2/13/2024 Approved JAVIER RAMOS JR
Final 2/13/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 2/13/2024 Approved JAVIER RAMOS JR
HVAC-Final 2/13/2024 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Not Ready JAVIER RAMOS JR
Service/Power Release 2/13/2024 Not Ready for Inspection JAVIER RAMOS JR
Underground Mechanical 2/13/2024 Approved JAVIER RAMOS JR
Final 6/24/2024 Partial Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Not Ready JAVIER RAMOS JR
Service/Power Release 6/24/2024 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Approved JAVIER RAMOS JR
Final 8/13/2024 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 8/13/2024 Approved JAVIER RAMOS JR