11605 W BURBANK BLVD 91601
Certificate Information: 11605 W BURBANK BLVD 91601
- Application / Permit
- 21010-20000-05362
- Plan Check / Job No.
- B21VN13938
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED 2-STORY ADU OVER 3-CAR GARAGE PER ORDINANCE.
- Permit Issued
- Issued on 3/13/2023
- Issuing Office
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | MICHAEL LOPEZ |
| Corrections Issued | 11/26/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 11/29/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/21/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 3/2/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 3/16/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 4/8/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/18/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/7/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/1/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 3/2/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 3/8/2023 | MICHAEL LOPEZ |
| Issued | 3/13/2023 | APPLICANT |
| CofO in Progress | 3/18/2025 | CHRISTOPHER ROJAS |
| CofO in Progress | 4/2/2025 | JUAN VALENZUELA |
| CofO in Progress | 4/3/2025 | CHRISTOPHER ROJAS |
| CofO in Progress | 4/23/2025 | JUAN VALENZUELA |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
| CofO Issued | 4/24/2025 | RUBEN SALAS |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2021 | AMIR KASHFI |
| "Q" conditions | Cleared | 12/7/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 12/7/2021 | AMIR KASHFI |
| Redevelopment Project Area | Cleared | 1/20/2022 | DAVID URITA |
| Miscellaneous | Cleared | 3/1/2022 | MIGUEL GAMBOA |
| Construction near power lines | Cleared | 3/14/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/28/2023 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 3/3/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/17/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/29/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 8/15/2024 | Approved | CHRISTOPHER ROJAS |
| Deputy Steel/Welding | 10/8/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/10/2024 | Partial Approval | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 10/10/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 11/12/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Shotcrete | 11/12/2024 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 11/12/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 11/12/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/12/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 11/12/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/12/2024 | Approved | CHRISTOPHER ROJAS |
| Deputy Shotcrete | 11/14/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 11/15/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/19/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 11/19/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/19/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 12/2/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Underground Mechanical | 12/2/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Special/Order Compliance | 12/3/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Shotcrete | 12/11/2024 | Conditional Approval | ROBERT GOLD |
| Insulation | 12/11/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/11/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/16/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 2/3/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 2/3/2025 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 2/3/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 2/3/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 2/3/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 2/7/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 2/7/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 3/17/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Deputy Shotcrete | 3/24/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Shotcrete | 3/26/2025 | Conditional Approval | JUAN VALENZUELA |
| Final | 4/4/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 4/23/2025 | OK to Issue CofO | JUAN VALENZUELA |