4225 N TOLUCA ROAD 91602

Certificate Information: 4225 N TOLUCA ROAD 91602

Application / Permit
21010-20000-05329
Plan Check / Job No.
B21VN13859
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED 4-CAR GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 8/10/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 NILOOFAR MEHRAIN
Corrections Issued 11/9/2021 NILOOFAR MEHRAIN
Quality Review Completed 11/10/2021 STEVEN KIM
Building Plans Picked Up 12/15/2021 APPLICANT
Applicant returned to address corrections 3/24/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/19/2022 NILOOFAR MEHRAIN
Plan Check Approved 8/2/2022 NILOOFAR MEHRAIN
Issued 8/10/2022 APPLICANT
CofO in Progress 1/24/2025 CHRISTOPHER ROJAS
Permit Finaled 2/6/2025 RUBEN SALAS
CofO Issued 2/6/2025 RUBEN SALAS
Permit Finaled 2/6/2025 RUBEN SALAS

Permit Application Clearance Information

ZA Case Cleared 3/16/2022 MIGUEL GAMBOA
Hydrant and Access approval Cleared 4/22/2022 DWAYNE LAURENT
Address approval Cleared 5/13/2022 CARLOS AGUILERA
Permit Cleared 5/13/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/16/2022 CARLOS AGUILERA
Sewer availability Cleared 5/16/2022 CARLOS AGUILERA
Trees in Parkway Cleared 5/24/2022 ADALBERTO VERA
Low Impact Development Cleared 7/6/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 7/6/2022 CARLOS AGUILERA

Contact Information

Contractor Property Services And Development Inc; Lic. No.: 833190-B 6711 FOREST LAWN DRIVE #105      LOS ANGELES, CA 90068
Engineer Kaddorah,, Salim Izzat; Lic. No.: C43757 PO BOX 546      HERMOSA BEACH, CA 90254

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/31/2022 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 9/15/2022 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 9/28/2022 Partial Approval GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 9/28/2022 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 10/5/2022 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 10/14/2022 Approved JACK KARGODORIAN
Deputy Reinf. Concrete 10/18/2022 Partial Approval JACK KARGODORIAN
Deputy Steel/Welding 11/17/2022 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Corrections Issued JACK KARGODORIAN
Deputy Wood Construction 4/6/2023 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 6/15/2023 Approved JACK KARGODORIAN
HVAC-Rough 6/15/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 6/15/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 6/27/2023 Approved JUAN VALENZUELA
ELECTRICAL-Rough 6/27/2023 Corrections Issued JUAN VALENZUELA
Green Building Rough 6/27/2023 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 6/27/2023 Approved JUAN VALENZUELA
Deputy Wood Construction 6/28/2023 Conditional Approval DAVID MATSON
Drywall Nailing 9/22/2023 Approved JACK KARGODORIAN
Shower Pan 9/26/2023 Approved THOMAS FINNILA
Footing/Foundation/Slab 10/11/2023 Not Ready for Inspection JOHN COLEMAN
Interior/Exterior Lathing 10/17/2023 Approved RYAN SALAZAR
Shower Pan 10/17/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 5/17/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/17/2024 Corrections Issued CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 5/17/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 5/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 5/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Pre-Inspection 5/29/2024 Partial Approval CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 5/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 5/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 6/6/2024 Approved CHRISTOPHER ROJAS
Final 7/24/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/24/2024 Approved CHRISTOPHER ROJAS
Green Building Final 7/24/2024 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/24/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 7/24/2024 Approved CHRISTOPHER ROJAS
Final 11/14/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 11/14/2024 Approved CHRISTOPHER ROJAS
Final 1/24/2025 OK to Issue CofO CHRISTOPHER ROJAS