15172 W POLK ST 91342

Certificate Information: 15172 W POLK ST 91342

Application / Permit
21010-20000-05305
Plan Check / Job No.
B21VN13792
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24'-8" X 48'-8" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER ENGINEERING. [THE LID CLEARANCE HAS BEEN DEFERRED. APPROVAL FOR LID REQUIREMENTS SHALL BE OBTAINED FROM LASAN PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY]
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 10/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 10/15/2021 JENNIFER LEE
Corrections Issued 10/19/2021 JENNIFER LEE
Applicant returned to address corrections 4/5/2022 OMAR GARNICA
Plan Check Approved 5/2/2022 OMAR GARNICA
Building Plans Picked Up 5/5/2022 APPLICANT
Issued 5/17/2022 APPLICANT
CofO in Progress 9/8/2023 JENNIFER RABUCHIN
CofO Issued 10/24/2023 RUBEN SALAS
Permit Finaled 10/24/2023 RUBEN SALAS

Permit Application Clearance Information

ZA Case Cleared 11/2/2021 LAUREN PADICK
Address approval Cleared 1/12/2022 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 1/14/2022 MARKOS PEREZ-BRAN
Permit Cleared 1/14/2022 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 1/14/2022 MARKOS PEREZ-BRAN
Sewer availability Cleared 1/14/2022 MARKOS PEREZ-BRAN
Construction near power lines Cleared 1/28/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 2/10/2022 MATTHEW CRAIG
GPI Written Notices Cleared 4/5/2022 OMAR GARNICA
Grading Pre-Inspection Cleared 4/5/2022 OMAR GARNICA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/5/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 8/4/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 8/15/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Partial Approval JENNIFER RABUCHIN
Green Building Rough 9/9/2022 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 9/9/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/19/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/19/2022 Approved JENNIFER RABUCHIN
Green Building Rough 10/19/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 10/19/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 10/19/2022 Approved JENNIFER RABUCHIN
Insulation 11/17/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/17/2022 Partial Approval JENNIFER RABUCHIN
Shower Pan 11/17/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 11/30/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/30/2022 Approved JENNIFER RABUCHIN
Underground Mechanical 2/3/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/1/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/1/2023 Corrections Issued JENNIFER RABUCHIN
Final 5/1/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/1/2023 Approved JENNIFER RABUCHIN
Green Building Rough 5/1/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/1/2023 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 5/1/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/2/2023 Approved JENNIFER RABUCHIN
Final 6/2/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 6/2/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/2/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/2/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 6/2/2023 Not Ready for Inspection JENNIFER RABUCHIN
Final 9/11/2023 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 9/11/2023 Not Required JENNIFER RABUCHIN