15172 W POLK ST 91342
Certificate Information: 15172 W POLK ST 91342
- Application / Permit
- 21010-20000-05305
- Plan Check / Job No.
- B21VN13792
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'-8" X 48'-8" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER ENGINEERING. [THE LID CLEARANCE HAS BEEN DEFERRED. APPROVAL FOR LID REQUIREMENTS SHALL BE OBTAINED FROM LASAN PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY]
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2021 | JENNIFER LEE |
| Corrections Issued | 10/19/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 4/5/2022 | OMAR GARNICA |
| Plan Check Approved | 5/2/2022 | OMAR GARNICA |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| Issued | 5/17/2022 | APPLICANT |
| CofO in Progress | 9/8/2023 | JENNIFER RABUCHIN |
| CofO Issued | 10/24/2023 | RUBEN SALAS |
| Permit Finaled | 10/24/2023 | RUBEN SALAS |
Permit Application Clearance Information
| ZA Case | Cleared | 11/2/2021 | LAUREN PADICK |
| Address approval | Cleared | 1/12/2022 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2022 | MARKOS PEREZ-BRAN |
| Permit | Cleared | 1/14/2022 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 1/14/2022 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 1/14/2022 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 1/28/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 2/10/2022 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 4/5/2022 | OMAR GARNICA |
| Grading Pre-Inspection | Cleared | 4/5/2022 | OMAR GARNICA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/5/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 8/4/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/15/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 9/9/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 9/9/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/19/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/19/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/19/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 10/19/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/19/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/17/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/17/2022 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 11/17/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/30/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/30/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 2/3/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/1/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/1/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/1/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 5/1/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 5/1/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 5/1/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/2/2023 | Approved | JENNIFER RABUCHIN |
| Final | 6/2/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 6/2/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/2/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 6/2/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 9/11/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 9/11/2023 | Not Required | JENNIFER RABUCHIN |