7099-7101 N BIANCA AVE 91406
Certificate Information: 7099-7101 N BIANCA AVE 91406
- Application / Permit
- 21010-20000-05302
- Plan Check / Job No.
- B21VN13779
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Conversion of (E) attached garage to (N) ADU
- Permit Issued
- Issued on 1/26/2022
- Issuing Office
- Current Status
- CofO Issued on 4/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2021 | HERNAN ARREOLA |
| Corrections Issued | 10/19/2021 | HERNAN ARREOLA |
| Plan Check Approved | 12/4/2021 | HERNAN ARREOLA |
| Issued | 1/26/2022 | APPLICANT |
| CofO in Progress | 7/22/2022 | VINCENT HANLEY |
| CofO Issued | 4/25/2023 | MICHAEL SMITH |
| Permit Finaled | 4/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2021 | ABEL CASILLAS |
| Sewer availability | Cleared | 11/17/2021 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2021 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/16/2022 | Not Ready for Inspection | SEAN HAUPT |
| Footing/Foundation/Slab | 2/17/2022 | Approved | SEAN HAUPT |
| Wood Frame | 3/10/2022 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/22/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 3/22/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 3/22/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/22/2022 | Approved | SEAN HAUPT |
| Insulation | 3/30/2022 | Corrections Issued | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 3/30/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| Gas Test | 4/8/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 4/18/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 4/18/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/18/2022 | Partial Approval | JUSTIN HAWLEY |
| Shower Pan | 4/18/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 5/19/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 7/11/2022 | Approved | VINCENT HANLEY |
| Final | 7/11/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/11/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/11/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 7/11/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/21/2022 | Approved | VINCENT HANLEY |
| Final | 7/21/2022 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 7/21/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/21/2022 | Approved | VINCENT HANLEY |