14245 W MAGNOLIA BLVD 91423

Certificate Information: 14245 W MAGNOLIA BLVD 91423

Application / Permit
21010-20000-05297
Plan Check / Job No.
B21VN13760
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 10/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 NILOOFAR MEHRAIN
Corrections Issued 11/2/2021 NILOOFAR MEHRAIN
Quality Review Completed 11/4/2021 STEVEN KIM
Building Plans Picked Up 11/12/2021 APPLICANT
Applicant returned to address corrections 9/15/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/11/2022 NILOOFAR MEHRAIN
Plan Check Approved 10/20/2022 NILOOFAR MEHRAIN
Issued 10/26/2022 APPLICANT
CofO in Progress 9/29/2025 RYAN SALAZAR
Permit Finaled 10/7/2025 RUBEN SALAS
CofO Issued 10/7/2025 RUBEN SALAS
Permit Finaled 10/7/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/6/2021 CARLOS AGUILERA
Permit Cleared 12/6/2021 CARLOS AGUILERA
Sewer availability Cleared 12/6/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/21/2022 CARLOS AGUILERA
Trees in Parkway Cleared 2/16/2022 ADALBERTO VERA
"Q" conditions Cleared 4/20/2022 NELSON RODRIGUEZ
"T" removal Cleared 4/20/2022 NELSON RODRIGUEZ
APC Cleared 4/20/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 4/20/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 4/20/2022 NELSON RODRIGUEZ
Hydrant and Access approval Cleared 5/16/2022 CINDY JOSSELYN
Low Impact Development Cleared 8/8/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/9/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Working Class American Construction; Lic. No.: 1053998-B 2232 W AVENUE L      LANCASTER, CA 93536

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/12/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 4/26/2023 Approved RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 4/27/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 8/11/2023 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 10/17/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 3/20/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 3/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 3/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/6/2024 Partial Approval RYAN SALAZAR
HVAC-Rough 5/6/2024 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 5/6/2024 Not Ready for Inspection RYAN SALAZAR
Sewer 5/6/2024 Approved RYAN SALAZAR
Underground Mechanical 5/13/2024 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 7/1/2024 Approved RYAN SALAZAR
Insulation 7/19/2024 Approved RYAN SALAZAR
Drywall Nailing 8/30/2024 Not Ready for Inspection RYAN SALAZAR
Drywall Nailing 9/5/2024 Approved RYAN SALAZAR
Service/Power Release 9/5/2024 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 10/17/2024 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 11/7/2024 Approved RYAN SALAZAR
Service/Power Release 6/12/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/11/2025 Corrections Issued RYAN SALAZAR
Final 9/11/2025 Not Ready for Inspection RYAN SALAZAR
Footing/Foundation/Slab 9/11/2025 Approved RYAN SALAZAR
Green Building Final 9/11/2025 Approved RYAN SALAZAR
Green Building Rough 9/11/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/11/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 9/11/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 9/11/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/25/2025 Approved RYAN SALAZAR
Deputy Wood Construction 9/25/2025 Conditional Approval RYAN SALAZAR
Final 9/25/2025 OK to Issue CofO RYAN SALAZAR