13737 W ADDISON ST 91423
Certificate Information: 13737 W ADDISON ST 91423
- Application / Permit
- 21010-20000-05295
- Plan Check / Job No.
- B21VN13757
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 18' X 26'6" DETACHED ACCESSORY DWELLING UNIT AS PER GCS 65852.2(E)(1)(B), NFPA-13D FIRE SPRINKLERS, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- CofO Issued on 1/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | RARES BODEA |
| Corrections Issued | 10/29/2021 | RARES BODEA |
| Quality Review Completed | 11/4/2021 | STEVEN KIM |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| Applicant returned to address corrections | 2/18/2022 | RARES BODEA |
| Plan Check Approved | 3/23/2022 | RARES BODEA |
| Issued | 3/23/2022 | APPLICANT |
| CofO in Progress | 1/4/2023 | MISAEL ESPARZA |
| CofO Issued | 1/9/2023 | RONALD MYRICK |
| Permit Finaled | 1/9/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/15/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 1/5/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/5/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 1/12/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 1/24/2022 | CARLOS AGUILERA |
| ZI | Cleared | 1/24/2022 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 2/23/2022 | LAURINDA MEADE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/13/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Reinf. Concrete | 4/20/2022 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/20/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 5/24/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 5/24/2022 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 5/26/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/31/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 5/31/2022 | Approved | MISAEL ESPARZA |
| Shower Pan | 6/1/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 6/2/2022 | Conditional Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/7/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2022 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 6/7/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/9/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 6/9/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 6/9/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/10/2022 | Partial Approval | MISAEL ESPARZA |
| Insulation | 6/14/2022 | Partial Inspection | MISAEL ESPARZA |
| Drywall Nailing | 6/21/2022 | Approved | CALEB MEISTER |
| Green Building Rough | 6/21/2022 | Approved | CALEB MEISTER |
| Insulation | 6/21/2022 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 12/13/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 12/13/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 12/13/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 12/13/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/13/2022 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 12/13/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 12/13/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/16/2022 | Approved | MISAEL ESPARZA |
| HVAC-Final | 12/16/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 12/16/2022 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| Final | 1/3/2023 | OK to Issue CofO | MISAEL ESPARZA |
| PLUMBING-Final | 1/3/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/3/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 1/3/2023 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 1/3/2023 | Approved | MISAEL ESPARZA |