19641 W MARTHA ST 91356
Certificate Information: 19641 W MARTHA ST 91356
- Application / Permit
- 21010-20000-05292
- Plan Check / Job No.
- B21VN13755
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 31'-11" x 29'-0" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 12/23/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 11/10/2021 | SARKIS HARABEDIAN |
| Quality Review Completed | 11/18/2021 | STEVEN KIM |
| Building Plans Picked Up | 11/22/2021 | APPLICANT |
| Applicant returned to address corrections | 11/22/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 12/23/2022 | SARKIS HARABEDIAN |
| Issued | 12/23/2022 | APPLICANT |
| CofO in Progress | 6/13/2025 | JON MCHUGH |
| Permit Finaled | 7/1/2025 | JOHN JANSON |
| CofO Issued | 7/1/2025 | JOHN JANSON |
| Permit Finaled | 7/1/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/9/2022 | DAGOVERTO GUERRERO |
| Trees in Parkway | Cleared | 10/7/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 11/17/2022 | ANDRES COVARRUBIAS |
| Permit | Cleared | 11/18/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 11/18/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 9/6/2023 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 9/15/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 9/15/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | JON MCHUGH |
| Insulation | 9/19/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Partial Approval | JON MCHUGH |
| Green Building Rough | 10/10/2023 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Rough | 10/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Verify Sprinkler Sign Off | 10/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Approved | JON MCHUGH |
| Green Building Rough | 11/3/2023 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Rough | 11/3/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 11/3/2023 | Corrections Issued | JON MCHUGH |
| Verify Sprinkler Sign Off | 11/3/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 1/29/2024 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 1/29/2024 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | JON MCHUGH |
| Green Building Rough | 1/31/2024 | Approved | JON MCHUGH |
| HVAC-Rough | 1/31/2024 | Approved | JON MCHUGH |
| PLUMBING-Rough | 1/31/2024 | Approved | JON MCHUGH |
| Underground Mechanical | 1/31/2024 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 1/31/2024 | Approved | JON MCHUGH |
| Insulation | 3/18/2024 | Corrections Issued | VINCENT HANLEY |
| Insulation | 3/20/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 3/27/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/1/2024 | Approved | KRISTEN CAUSEY |
| Underground Mechanical | 12/26/2024 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 1/6/2025 | Corrections Issued | JON MCHUGH |
| Sewer | 2/13/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 2/25/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 2/25/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Final | 3/10/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 3/10/2025 | Approved | JON MCHUGH |
| Service/Power Release | 3/10/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 3/13/2025 | Approved | JON MCHUGH |
| Final | 6/9/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 6/9/2025 | Approved | JON MCHUGH |
| MERV13>=Final | 6/9/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Not Ready | JON MCHUGH |
| SUSMP-Std. Urban Storm Water | 6/9/2025 | Approved | JON MCHUGH |
| Smoke Detectors | 6/9/2025 | Approved | JON MCHUGH |
| Final | 6/12/2025 | OK to Issue CofO | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | JON MCHUGH |