27745 S GRANDVIEW WAY 90732
Certificate Information: 27745 S GRANDVIEW WAY 90732
- Application / Permit
- 21010-20000-05277
- Plan Check / Job No.
- B21VN13719
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (TR 71866-01 PVSP-SUBAREA 3) PROPOSE THREE STORY SFD WITH ATTACHED GARAGE_PLAN 2C [BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D].
- Permit Issued
- Issued on 9/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | PETER MOSESIAN |
| Corrections Issued | 11/4/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 11/10/2021 | APPLICANT |
| Quality Review Completed | 4/7/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 4/7/2022 | PETER MOSESIAN |
| Plan Check Approved | 9/21/2022 | PETER MOSESIAN |
| Issued | 9/29/2022 | APPLICANT |
| CofO in Progress | 11/1/2023 | ANSON MAGLASANG |
| Permit Finaled | 11/1/2023 | ANSON MAGLASANG |
| CofO Issued | 11/1/2023 | ANSON MAGLASANG |
| Permit Finaled | 11/1/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| CPC | Cleared | 2/25/2022 | ANACANY HURTADO |
| CPC | Cleared | 2/25/2022 | ANACANY HURTADO |
| CPC | Cleared | 2/25/2022 | ANACANY HURTADO |
| CPC | Cleared | 2/25/2022 | ANACANY HURTADO |
| Frnt yard landscape/Water mgmt | Cleared | 2/25/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 2/25/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 2/25/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 2/25/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 2/25/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 2/25/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 2/25/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 2/25/2022 | ANACANY HURTADO |
| Private street | Cleared | 2/25/2022 | ANACANY HURTADO |
| Specific Plan | Cleared | 2/25/2022 | ANACANY HURTADO |
| Tract Map conditions | Cleared | 2/25/2022 | ANACANY HURTADO |
| Tract Map conditions | Cleared | 2/25/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 2/25/2022 | ANACANY HURTADO |
| Address approval | Cleared | 7/1/2022 | ERIK BEASLEY |
| Highway dedication | Cleared | 7/1/2022 | ERIK BEASLEY |
| Permit | Cleared | 7/1/2022 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 7/1/2022 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | ERIK BEASLEY |
| Low Impact Development | Cleared | 8/1/2022 | AMMAR ELTAWIL |
| Sewer availability | Cleared | 8/30/2022 | JOSE HERNANDEZ |
| Hydrant and Access approval | Cleared | 8/31/2022 | ROBERT DUFF |
Contact Information
| Architect | Kough,, Eric R; Lic. No.: C26497 | 2539 FAIRWAY DRIVE COSTA MESA, CA 92627 |
| Contractor | Owner-Builder | , |
| Engineer | Liu,, Haiyan Harry; Lic. No.: C81463 | 10855 BECKFORD AVE NORTHRIDGE, CA 91326 |
| Engineer | Van, Gaale, Mark Allan; Lic. No.: C58680 | 26772 DESERT LOCUST ST MURRIETA, CA 92562 |
| Geologist | Swiatek,, Mark A; Lic. No.: EG1781 | 24203 VALLEY ST NEWHALL, CA 91321 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/28/2023 | Partial Approval | ANSON MAGLASANG |
| Sewer | 3/29/2023 | Partial Approval | JAMES CHAVEZ |
| Deputy Reinf. Concrete | 4/28/2023 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 4/28/2023 | Approved | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 7/12/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Partial Approval | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 7/24/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 7/27/2023 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 8/1/2023 | Approved | ANSON MAGLASANG |
| Green Building Rough | 8/1/2023 | Approved | ANSON MAGLASANG |
| Insulation | 8/1/2023 | Approved | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 8/1/2023 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 8/7/2023 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 8/7/2023 | Partial Approval | ANSON MAGLASANG |
| Service/Power Release | 10/2/2023 | Approved | JAMES CHAVEZ |
| Final | 10/25/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Final | 10/25/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 10/25/2023 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 10/25/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 11/1/2023 | OK to Issue CofO | ANSON MAGLASANG |
| Green Building Final | 11/1/2023 | Approved | ANSON MAGLASANG |
| Smoke Detectors | 11/1/2023 | Approved | ANSON MAGLASANG |