18003 W OSBORNE ST 91325

Certificate Information: 18003 W OSBORNE ST 91325

Application / Permit
21010-20000-05239
Plan Check / Job No.
B21VN13690
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 76'-5" X 22'-10" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED GARAGE AND STORAGE The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 5/22/2022
Issuing Office
Current Status
CofO Issued on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 SELLA BENYAMIN
Corrections Issued 11/23/2021 SELLA BENYAMIN
Quality Review Completed 11/24/2021 STEVEN KIM
Building Plans Picked Up 11/24/2021 APPLICANT
Plan Check Approved 2/3/2022 SELLA BENYAMIN
Issued 5/22/2022 APPLICANT
CofO in Progress 6/16/2023 JAVIER RAMOS JR
Permit Finaled 7/18/2023 MICHAEL SMITH
CofO Issued 7/18/2023 MICHAEL SMITH
Permit Finaled 7/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/6/2021 JOSE DUARTE-DIAZ
Construction near power lines Cleared 12/20/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/22/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 1/22/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 1/25/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/25/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 6/8/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Corrections Issued DEANDRE HOFFMAN
ELECTRICAL-Rough 8/1/2022 Approved JAVIER RAMOS JR
HVAC-Rough 8/1/2022 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 8/8/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 8/8/2022 Approved JAVIER RAMOS JR
Underground Mechanical 8/23/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 9/20/2022 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Approved JAVIER RAMOS JR
Green Building Rough 9/20/2022 Not Ready for Inspection JAVIER RAMOS JR
Verify Sprinkler Sign Off 9/20/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/7/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 11/22/2022 Approved JAVIER RAMOS JR
Green Building Rough 11/22/2022 Approved JAVIER RAMOS JR
Insulation 11/22/2022 Corrections Issued JAVIER RAMOS JR
Insulation 12/1/2022 Approved JAVIER RAMOS JR
Pre-Inspection 12/1/2022 No Access for Inspection JAVIER RAMOS JR
Drywall Nailing 12/14/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/14/2022 Not Ready for Inspection JAVIER RAMOS JR
Shower Pan 12/14/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/29/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/23/2023 Corrections Issued JAVIER RAMOS JR
Final 3/23/2023 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 3/23/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/23/2023 SGSOV Not Ready JAVIER RAMOS JR
Service/Power Release 3/23/2023 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 3/23/2023 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 5/22/2023 Approved JAVIER RAMOS JR
Final 5/22/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 5/22/2023 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 5/22/2023 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 5/22/2023 Not Ready for Inspection JAVIER RAMOS JR
Pre-Inspection 5/22/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/22/2023 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 5/22/2023 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 5/22/2023 Approved JAVIER RAMOS JR
Final 6/15/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 6/15/2023 Approved JAVIER RAMOS JR