5152 N VELOZ AVE 91356

Certificate Information: 5152 N VELOZ AVE 91356

Application / Permit
21010-20000-05226
Plan Check / Job No.
B21VN13654
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 39'-0" x 21'-7" DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). " NFPA 13-D FIRE SPRINKLERS THRU-OUT"
Permit Issued
Issued on 5/10/2022
Issuing Office
Current Status
CofO Issued on 4/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2021 APPLICANT
Assigned to Plan Check Engineer 11/11/2021 SARKIS HARABEDIAN
Corrections Issued 11/17/2021 SARKIS HARABEDIAN
Quality Review Completed 11/23/2021 STEVEN KIM
Applicant returned to address corrections 4/25/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 5/6/2022 SARKIS HARABEDIAN
Plan Check Approved 5/10/2022 SARKIS HARABEDIAN
Issued 5/10/2022 APPLICANT
Building Plans Picked Up 5/10/2022 APPLICANT
CofO in Progress 4/21/2023 DAVID SANDOVAL
Permit Finaled 4/21/2023 JOHN JANSON
CofO Issued 4/21/2023 JOHN JANSON
Permit Finaled 4/21/2023 JOHN JANSON

Permit Application Clearance Information

GPI Written Notices Cleared 11/17/2021 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 11/17/2021 SARKIS HARABEDIAN
Low Impact Development Cleared 12/22/2021 TA ANH
Address approval Cleared 2/4/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/4/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/4/2022 CARLOS AGUILERA
Sewer availability Cleared 2/4/2022 CARLOS AGUILERA
Construction near power lines Cleared 3/18/2022 WALTER RAMIREZ
Hydrant and Access approval Cleared 4/18/2022 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/26/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 5/26/2022 Partial Approval DAVID SANDOVAL
Underground Mechanical 5/26/2022 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 6/6/2022 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 8/25/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Partial Approval DAVID SANDOVAL
Gas Test 8/25/2022 Partial Inspection DAVID SANDOVAL
HVAC-Rough 8/25/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 8/25/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 9/23/2022 Approved DAVID SANDOVAL
Green Building Rough 9/23/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 9/23/2022 Partial Approval DAVID SANDOVAL
Shower Pan 9/23/2022 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 9/23/2022 Approved DAVID SANDOVAL
Drywall Nailing 9/30/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/31/2022 Approved DAVID SANDOVAL
Underground Mechanical 1/4/2023 Approved DAVID SANDOVAL
ELECTRICAL-Final 3/28/2023 Approved DAVID SANDOVAL
Final 3/28/2023 Corrections Issued DAVID SANDOVAL
Green Building Final 3/28/2023 Approved DAVID SANDOVAL
HVAC-Final 3/28/2023 Approved DAVID SANDOVAL
PLUMBING-Final 3/28/2023 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved DAVID SANDOVAL
Service/Power Release 3/28/2023 Approved DAVID SANDOVAL
Smoke Detectors 3/28/2023 Approved DAVID SANDOVAL
Verify Rec and Parks Fee Memo 3/28/2023 Approved DAVID SANDOVAL
Final 4/21/2023 OK to Issue CofO DAVID SANDOVAL