14243 W MAGNOLIA BLVD 91423
Certificate Information: 14243 W MAGNOLIA BLVD 91423
- Application / Permit
- 21010-20000-05216
- Plan Check / Job No.
- B21VN13617
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 18'-6" X 20' (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED 20' X 20' GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | SELLA BENYAMIN |
| Corrections Issued | 11/2/2021 | SELLA BENYAMIN |
| Quality Review Completed | 11/4/2021 | STEVEN KIM |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| Plan Check Approved | 9/29/2022 | SELLA BENYAMIN |
| Issued | 10/20/2022 | APPLICANT |
| CofO in Progress | 10/16/2025 | RYAN SALAZAR |
| Permit Finaled | 11/4/2025 | RUBEN SALAS |
| CofO Issued | 11/4/2025 | RUBEN SALAS |
| Permit Finaled | 11/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2021 | CARLOS AGUILERA |
| Permit | Cleared | 12/2/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/2/2021 | CARLOS AGUILERA |
| "Q" conditions | Cleared | 12/3/2021 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2022 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 4/6/2022 | ADALBERTO VERA |
| "T" removal | Cleared | 4/19/2022 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 4/19/2022 | NELSON RODRIGUEZ |
| Hydrant and Access approval | Cleared | 4/21/2022 | LAURINDA MEADE |
| Low Impact Development | Cleared | 8/22/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/23/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Working Class American Construction; Lic. No.: 1053998-B | 2232 W AVENUE L LANCASTER, CA 93536 |
| Engineer | Khansa,, Eyass Wafik; Lic. No.: C91758 | 2252 JOSIE AVE LONG BEACH, CA 90815 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/27/2022 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 11/28/2022 | Not Ready for Inspection | JOHN COLEMAN |
| Special/Order Compliance | 4/6/2023 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 5/19/2023 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 5/26/2023 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 6/9/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 7/10/2023 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 8/23/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/17/2023 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/20/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 3/20/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 3/20/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/6/2024 | Partial Approval | RYAN SALAZAR |
| HVAC-Rough | 5/6/2024 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 5/6/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Sewer | 5/6/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 5/13/2024 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 6/25/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 7/1/2024 | Approved | RYAN SALAZAR |
| Insulation | 7/19/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/30/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/17/2024 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 12/23/2024 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Final | 12/23/2024 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Final | 12/23/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Service/Power Release | 12/23/2024 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 3/7/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Final | 3/7/2025 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 4/2/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Final | 4/2/2025 | Partial Approval | RYAN SALAZAR |
| Service/Power Release | 4/2/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Service/Power Release | 4/15/2025 | Approved | RYAN SALAZAR |
| Service/Power Release | 6/12/2025 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 8/14/2025 | Corrections Issued | RYAN SALAZAR |
| HVAC-Final | 8/14/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Final | 8/14/2025 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/11/2025 | Corrections Issued | RYAN SALAZAR |
| Final | 9/11/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 9/11/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 9/11/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/11/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/11/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 9/11/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 9/11/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/25/2025 | Approved | RYAN SALAZAR |
| Final | 9/25/2025 | Partial Approval | RYAN SALAZAR |
| Final | 10/17/2025 | OK to Issue CofO | RYAN SALAZAR |