14253 W MAGNOLIA BLVD 91423

Certificate Information: 14253 W MAGNOLIA BLVD 91423

Application / Permit
21010-20000-05210
Plan Check / Job No.
B21VN13602
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 18'-6" X 20' (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED 20' X 20' GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 11/9/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 SELLA BENYAMIN
Corrections Issued 11/2/2021 SELLA BENYAMIN
Quality Review Completed 11/4/2021 STEVEN KIM
Building Plans Picked Up 11/12/2021 APPLICANT
Plan Check Approved 9/29/2022 SELLA BENYAMIN
Issued 11/9/2022 APPLICANT
CofO in Progress 11/21/2025 RYAN SALAZAR
Permit Finaled 12/4/2025 RUBEN SALAS
CofO Issued 12/4/2025 RUBEN SALAS
Permit Finaled 12/4/2025 RUBEN SALAS

Permit Application Clearance Information

"Q" conditions Cleared 11/23/2021 LAUREN PADICK
"T" removal Cleared 11/23/2021 LAUREN PADICK
Miscellaneous Cleared 11/23/2021 LAUREN PADICK
Address approval Cleared 12/2/2021 CARLOS AGUILERA
Permit Cleared 12/2/2021 CARLOS AGUILERA
Sewer availability Cleared 12/2/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/21/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/3/2022 JOHN CONNEALLY
Trees in Parkway Cleared 3/2/2022 ADALBERTO VERA
Low Impact Development Cleared 8/25/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 11/9/2022 DAGOVERTO GUERRERO
Hold Cleared 12/27/2022 MARIA VENDIVIL

Contact Information

Contractor Working Class American Construction; Lic. No.: 1053998-B 2232 W AVENUE L      LANCASTER, CA 93536

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/28/2022 Not Ready for Inspection JOHN COLEMAN
Footing/Foundation/Slab 12/28/2022 Approved JOHN COLEMAN
PLUMBING-Rough 4/17/2023 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 4/20/2023 Partial Inspection RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 4/24/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 7/10/2023 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 8/11/2023 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 10/17/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 3/20/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 3/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 3/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/6/2024 Partial Approval RYAN SALAZAR
HVAC-Rough 5/6/2024 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 5/6/2024 Not Ready for Inspection RYAN SALAZAR
Sewer 5/6/2024 Approved RYAN SALAZAR
Underground Mechanical 5/13/2024 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 7/1/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 8/8/2024 Corrections Issued RYAN SALAZAR
Insulation 8/8/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 9/12/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/13/2025 Approved RYAN SALAZAR
Service/Power Release 6/12/2025 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Final 6/25/2025 Approved RYAN SALAZAR
Service/Power Release 6/25/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 11/7/2025 No Access for Inspection MISAEL ESPARZA
Final 11/7/2025 No Access for Inspection MISAEL ESPARZA
Green Building Final 11/7/2025 No Access for Inspection MISAEL ESPARZA
Green Building Rough 11/7/2025 No Access for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 11/7/2025 No Access for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 11/7/2025 No Access for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 11/13/2025 Approved RYAN SALAZAR
Final 11/13/2025 OK to Issue CofO RYAN SALAZAR
Green Building Final 11/13/2025 Approved RYAN SALAZAR
Green Building Rough 11/13/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 11/13/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 11/13/2025 Approved RYAN SALAZAR