14263 W MAGNOLIA BLVD 91423

Certificate Information: 14263 W MAGNOLIA BLVD 91423

Application / Permit
21010-20000-05206
Plan Check / Job No.
B21VN13588
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 20' GARAGE WITH ATTACHED 18'-6' X 20' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 SELLA BENYAMIN
Corrections Issued 10/26/2021 SELLA BENYAMIN
Quality Review Completed 10/28/2021 STEVEN KIM
Building Plans Picked Up 10/29/2021 APPLICANT
Applicant returned to address corrections 9/15/2022 SELLA BENYAMIN
Plan Check Approved 9/16/2022 SELLA BENYAMIN
Issued 9/27/2022 APPLICANT
CofO in Progress 2/3/2026 RYAN SALAZAR
Permit Finaled 2/5/2026 RICHARD STEINBACH
CofO Issued 2/5/2026 RICHARD STEINBACH
Permit Finaled 2/5/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 12/2/2021 CARLOS AGUILERA
Permit Cleared 12/2/2021 CARLOS AGUILERA
Sewer availability Cleared 12/2/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/21/2022 CARLOS AGUILERA
Trees in Parkway Cleared 3/2/2022 ADALBERTO VERA
"Q" conditions Cleared 4/20/2022 NELSON RODRIGUEZ
"T" removal Cleared 4/20/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 4/20/2022 NELSON RODRIGUEZ
Hydrant and Access approval Cleared 4/26/2022 DWIGHT SANKEY
Low Impact Development Cleared 8/3/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/8/2022 LEE GUILBEAUX

Contact Information

Contractor Working Class American Construction; Lic. No.: 1053998-B 2232 W AVENUE L      LANCASTER, CA 93536
Engineer Khansa,, Eyass Wafik; Lic. No.: C91758 2252 JOSIE AVE      LONG BEACH, CA 90815

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/9/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 4/17/2023 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 4/19/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 7/10/2023 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 8/9/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 9/6/2023 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 10/17/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 3/20/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 3/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 3/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Underground Mechanical 5/13/2024 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 6/24/2024 Corrections Issued DAVID ANDERSON
Rough-Elec/Plmb/HVAC 7/1/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 8/8/2024 Corrections Issued RYAN SALAZAR
Insulation 8/8/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 9/25/2024 Approved JACK KARGODORIAN
ELECTRICAL-Final 6/25/2025 Approved RYAN SALAZAR
Service/Power Release 6/25/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 1/12/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 1/12/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 1/12/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 1/12/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/12/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 1/12/2026 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 1/12/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 1/12/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 1/16/2026 Corrections Issued RAUL OLAGI
Final 1/16/2026 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 1/16/2026 Approved RAUL OLAGI
Green Building Final 1/16/2026 Approved RAUL OLAGI
Green Building Rough 1/16/2026 Approved RAUL OLAGI
HVAC-Final 1/16/2026 Corrections Issued RAUL OLAGI
PLUMBING-Final 1/16/2026 Corrections Issued RAUL OLAGI
Smoke Detectors 1/16/2026 Approved RAUL OLAGI
BUILDING-Rough-Frame 1/23/2026 Approved RYAN SALAZAR
Final 1/23/2026 Partial Approval RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 1/23/2026 SGSOV Approved RYAN SALAZAR
Verify Sprinkler Sign Off 1/23/2026 Approved RYAN SALAZAR
Deputy Wood Construction 2/4/2026 Conditional Approval RYAN SALAZAR
Final 2/4/2026 OK to Issue CofO RYAN SALAZAR