220 N BONHILL ROAD 90049
Certificate Information: 220 N BONHILL ROAD 90049
- Application / Permit
- 21010-20000-05146
- Plan Check / Job No.
- B21VN13509
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25'-8" x 27'-8" DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 12/15/2022
- Issuing Office
- Current Status
- CofO Issued on 5/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | SEAN SHAHMIRI |
| Corrections Issued | 12/14/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 12/17/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/21/2021 | APPLICANT |
| Plan Check Approved | 12/15/2022 | SEAN SHAHMIRI |
| Issued | 12/15/2022 | APPLICANT |
| CofO in Progress | 4/24/2024 | KEVIN SARGSYAN |
| Permit Finaled | 5/4/2024 | DANIEL ORRANTE |
| CofO Issued | 5/4/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/4/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2022 | STEVEN JIN |
| Sewer availability | Cleared | 8/12/2022 | STEVEN JIN |
| Address approval | Cleared | 10/5/2022 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 10/5/2022 | HISASHI KOBAYAKAWA |
| ZA Case | Cleared | 10/21/2022 | DANG NGUYEN |
| Low Impact Development | Cleared | 11/29/2022 | DEBORA LEITE |
| Hydrant and Access approval | Cleared | 11/30/2022 | RUEL COLE |
| Roof/Waste drainage to street | Cleared | 12/2/2022 | DINAH GARIN |
| Construction near power lines | Cleared | 12/15/2022 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/18/2023 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 1/23/2023 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/23/2023 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2023 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 2/27/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/27/2023 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 3/3/2023 | Approved | KEVIN SARGSYAN |
| Sewer | 3/13/2023 | Approved | KEVIN SARGSYAN |
| Shower Pan | 3/13/2023 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 3/13/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/23/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 3/23/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/18/2023 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2023 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/24/2023 | Conditional Approval | KEVIN SARGSYAN |
| Green Building Rough | 4/24/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 4/27/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 5/2/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/10/2023 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 7/26/2023 | No Access for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 7/26/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Service/Power Release | 7/26/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Smoke Detectors | 7/26/2023 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/28/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 7/28/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/11/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 8/11/2023 | Approved | KEVIN SARGSYAN |
| Final | 8/11/2023 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 8/11/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 8/11/2023 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 8/11/2023 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 8/11/2023 | Approved | KEVIN SARGSYAN |
| Final | 4/23/2024 | OK to Issue CofO | KEVIN SARGSYAN |
| Service/Power Release | 4/23/2024 | Approved | KEVIN SARGSYAN |