6132 N WILBUR AVE 91335
Certificate Information: 6132 N WILBUR AVE 91335
- Application / Permit
- 21010-20000-05136
- Plan Check / Job No.
- B21VN13454
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 7/1/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2021 | SELLA BENYAMIN |
| Corrections Issued | 10/19/2021 | SELLA BENYAMIN |
| Quality Review Completed | 10/21/2021 | STEVEN KIM |
| Applicant returned to address corrections | 4/26/2022 | SELLA BENYAMIN |
| Plan Check Approved | 6/24/2022 | SELLA BENYAMIN |
| Issued | 7/1/2022 | APPLICANT |
| CofO in Progress | 8/13/2025 | JON MCHUGH |
| Permit Finaled | 9/12/2025 | MICHAEL PELHAM |
| CofO Issued | 9/12/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/12/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/31/2022 | CARLOS AGUILERA |
| ZI | Cleared | 4/21/2022 | PABLO ESTRADA |
| Low Impact Development | Cleared | 5/12/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/17/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/17/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 11/23/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/23/2022 | Corrections Issued | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 12/28/2022 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 12/28/2022 | Not Ready for Inspection | JON MCHUGH |
| Verify Sprinkler Sign Off | 12/28/2022 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 12/28/2022 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 3/6/2023 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 3/23/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 4/11/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 4/11/2023 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 4/27/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 5/18/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Approved | JON MCHUGH |
| Green Building Rough | 5/18/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 5/18/2023 | Approved | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 5/18/2023 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 5/18/2023 | Approved | JON MCHUGH |
| Wood Frame | 5/18/2023 | Approved | JON MCHUGH |
| Insulation | 6/21/2023 | Approved | JON MCHUGH |
| Sewer | 6/21/2023 | Corrections Issued | JON MCHUGH |
| Drywall Nailing | 7/19/2023 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 7/20/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 9/13/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 2/26/2024 | Approved | JON MCHUGH |
| Sewer | 12/2/2024 | Approved | JON MCHUGH |
| Special/Order Compliance | 12/2/2024 | Corrections Issued | JON MCHUGH |
| Final | 2/25/2025 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 2/25/2025 | Approved | JON MCHUGH |
| Green Building Final | 2/25/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 2/25/2025 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 2/25/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 3/24/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 3/24/2025 | Not Ready for Inspection | JON MCHUGH |
| Gas Test | 3/24/2025 | Approved | JON MCHUGH |
| Green Building Final | 3/24/2025 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 3/24/2025 | Not Ready for Inspection | JON MCHUGH |
| Service/Power Release | 3/24/2025 | Approved | JON MCHUGH |
| Smoke Detectors | 3/24/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 7/25/2025 | Approved | JON MCHUGH |
| Final | 7/25/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 7/25/2025 | Approved | JON MCHUGH |
| HVAC-Final | 7/25/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 7/25/2025 | Approved | JON MCHUGH |
| Smoke Detectors | 7/25/2025 | Approved | JON MCHUGH |
| Final | 8/13/2025 | OK to Issue CofO | JON MCHUGH |