15757 W MARLIN PL 91406

Certificate Information: 15757 W MARLIN PL 91406

Application / Permit
21010-20000-05129
Plan Check / Job No.
B21VN13432
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 8/2/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2021 APPLICANT
Assigned to Plan Check Engineer 10/20/2021 JEROME MAGAT PALMA
Corrections Issued 10/20/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 5/28/2022 JEROME MAGAT PALMA
Plan Check Approved 6/12/2022 JEROME MAGAT PALMA
Building Plans Picked Up 6/14/2022 APPLICANT
Issued 8/2/2022 APPLICANT
CofO in Progress 8/18/2023 RAUL OLAGI
Permit Finaled 8/30/2023 RUBEN SALAS
CofO Issued 8/30/2023 RUBEN SALAS
Permit Finaled 8/30/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/17/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/22/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 12/22/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 5/3/2022 CHRIS VONG
Construction near power lines Cleared 5/13/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 5/16/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/30/2022 Partial Approval RAUL OLAGI
Sewer 9/30/2022 Approved RAUL OLAGI
Underground Mechanical 9/30/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 10/18/2022 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 10/25/2022 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 10/28/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 10/28/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 12/30/2022 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 12/30/2022 Not Ready for Inspection RAUL OLAGI
Green Building Rough 12/30/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 12/30/2022 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 12/30/2022 Not Ready for Inspection RAUL OLAGI
MERV13>=Rough 12/30/2022 Not Ready for Inspection RAUL OLAGI
Verify Sprinkler Sign Off 12/30/2022 Approved RAUL OLAGI
Wood Frame 3/7/2023 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 3/8/2023 Approved RAUL OLAGI
Green Building Rough 3/8/2023 Approved RAUL OLAGI
MERV13>=Rough 3/8/2023 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 3/8/2023 Approved RAUL OLAGI
Underground Mechanical 3/8/2023 Partial Approval RAUL OLAGI
Insulation 3/15/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 3/15/2023 Partial Approval RAUL OLAGI
Special/Order Compliance 3/16/2023 Corrections Issued RAUL OLAGI
Drywall Nailing 4/20/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 4/20/2023 Not Ready for Inspection RAUL OLAGI
Shower Pan 4/20/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 4/28/2023 Approved RAUL OLAGI
Shower Pan 4/28/2023 Approved RAUL OLAGI
ELECTRICAL-Final 7/10/2023 Corrections Issued RAUL OLAGI
Final 7/10/2023 Corrections Issued RAUL OLAGI
HVAC-Final 7/10/2023 Approved RAUL OLAGI
PLUMBING-Final 7/10/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Final 8/18/2023 Approved RAUL OLAGI
Final 8/18/2023 OK to Issue CofO RAUL OLAGI
Green Building Final 8/18/2023 Approved RAUL OLAGI
MERV13>=Final 8/18/2023 Approved RAUL OLAGI
PLUMBING-Final 8/18/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Approved RAUL OLAGI
Service/Power Release 8/18/2023 Approved RAUL OLAGI
Smoke Detectors 8/18/2023 Approved RAUL OLAGI