15757 W MARLIN PL 91406
Certificate Information: 15757 W MARLIN PL 91406
- Application / Permit
- 21010-20000-05129
- Plan Check / Job No.
- B21VN13432
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 10/20/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 5/28/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 6/12/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 6/14/2022 | APPLICANT |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 8/18/2023 | RAUL OLAGI |
| Permit Finaled | 8/30/2023 | RUBEN SALAS |
| CofO Issued | 8/30/2023 | RUBEN SALAS |
| Permit Finaled | 8/30/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 12/22/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 5/3/2022 | CHRIS VONG |
| Construction near power lines | Cleared | 5/13/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 5/16/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/30/2022 | Partial Approval | RAUL OLAGI |
| Sewer | 9/30/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 9/30/2022 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 10/18/2022 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 10/25/2022 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/28/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 10/28/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/30/2022 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 12/30/2022 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Rough | 12/30/2022 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 12/30/2022 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 12/30/2022 | Not Ready for Inspection | RAUL OLAGI |
| MERV13>=Rough | 12/30/2022 | Not Ready for Inspection | RAUL OLAGI |
| Verify Sprinkler Sign Off | 12/30/2022 | Approved | RAUL OLAGI |
| Wood Frame | 3/7/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/8/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 3/8/2023 | Approved | RAUL OLAGI |
| MERV13>=Rough | 3/8/2023 | Approved | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 3/8/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 3/8/2023 | Partial Approval | RAUL OLAGI |
| Insulation | 3/15/2023 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 3/15/2023 | Partial Approval | RAUL OLAGI |
| Special/Order Compliance | 3/16/2023 | Corrections Issued | RAUL OLAGI |
| Drywall Nailing | 4/20/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/20/2023 | Not Ready for Inspection | RAUL OLAGI |
| Shower Pan | 4/20/2023 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 4/28/2023 | Approved | RAUL OLAGI |
| Shower Pan | 4/28/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 7/10/2023 | Corrections Issued | RAUL OLAGI |
| Final | 7/10/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 7/10/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 7/10/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 8/18/2023 | Approved | RAUL OLAGI |
| Final | 8/18/2023 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 8/18/2023 | Approved | RAUL OLAGI |
| MERV13>=Final | 8/18/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 8/18/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 8/18/2023 | Approved | RAUL OLAGI |
| Smoke Detectors | 8/18/2023 | Approved | RAUL OLAGI |