6911 N WYSTONE AVE 91335

Certificate Information: 6911 N WYSTONE AVE 91335

Application / Permit
21010-20000-05120
Plan Check / Job No.
B21VN13407
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan 182sqft addition to existing detached garage (18'-2"x24-2")of 438sqft to be converted into a accessory dwelling unit totaling Per ordinance and LAMC 12.22 A 33 (c) &(d)
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
CofO Issued on 2/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2021 APPLICANT
Assigned to Plan Check Engineer 10/5/2021 ZAW HAN
Corrections Issued 10/6/2021 ZAW HAN
Plan Check Approved 1/12/2022 ZAW HAN
Issued 4/25/2022 APPLICANT
CofO in Progress 2/6/2024 JEFFREY BULL
Permit Finaled 2/16/2024 JOHN JANSON
CofO Issued 2/16/2024 JOHN JANSON
Permit Finaled 2/16/2024 JOHN JANSON

Permit Application Clearance Information

ZI Cleared 10/8/2021 DANG NGUYEN
Address approval Cleared 10/12/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/12/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 10/12/2021 CARLOS AGUILERA
Sewer availability Cleared 10/12/2021 CARLOS AGUILERA
Construction near power lines Cleared 1/7/2022 RIDWAN HARDY
Construction within easement Cleared 1/7/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Hoerner,, John Brent; Lic. No.: S2145 24024 VIA CANDELA      VALENCIA, CA 91355

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/23/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 8/30/2022 Partial Approval JEFFREY BULL
Green Building Rough 8/30/2022 Approved JEFFREY BULL
Pre-Inspection 8/30/2022 Approved JEFFREY BULL
Wood Frame 8/30/2022 Approved JEFFREY BULL
Pre-Inspection 7/3/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 9/18/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval JEFFREY BULL
Gas Test 9/18/2023 Approved JEFFREY BULL
PLUMBING-Rough 9/18/2023 Approved JEFFREY BULL
HVAC-Rough 9/29/2023 Approved JEFFREY BULL
Insulation 9/29/2023 Corrections Issued JEFFREY BULL
Interior/Exterior Lathing 9/29/2023 Partial Approval JEFFREY BULL
Insulation 10/3/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 10/3/2023 Partial Approval JEFFREY BULL
Rough-Elec/Plmb/HVAC 10/3/2023 Approved JEFFREY BULL
Drywall Nailing 10/10/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 10/10/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 1/25/2024 Approved JEFFREY BULL
Final 1/25/2024 Corrections Issued JEFFREY BULL
Green Building Final 1/25/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 1/25/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 1/25/2024 Approved JEFFREY BULL
Final 2/6/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 2/6/2024 Approved JEFFREY BULL