14626-14626 1/2 W GILMORE ST 91411
Certificate Information: 14626-14626 1/2 W GILMORE ST 91411
- Application / Permit
- 21010-20000-05101
- Plan Check / Job No.
- B21VN13314
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (40'-0"x30'-0"),1200 SQFT 1 STORY DETACHED ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 11/22/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | PETER MOSESIAN |
| Corrections Issued | 10/24/2021 | PETER MOSESIAN |
| Quality Review Completed | 11/8/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/10/2021 | APPLICANT |
| Applicant returned to address corrections | 8/23/2022 | PETER MOSESIAN |
| Plan Check Approved | 9/14/2022 | PETER MOSESIAN |
| Issued | 11/22/2022 | APPLICANT |
| CofO in Progress | 8/18/2025 | RYAN SALAZAR |
| CofO Issued | 9/23/2025 | RUBEN SALAS |
| Permit Finaled | 9/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/28/2021 | LEE GUILBEAUX |
| "Q" conditions | Cleared | 12/13/2021 | PABLO ESTRADA |
| Construction near power lines | Cleared | 12/22/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/13/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/26/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/29/2022 | LEE GUILBEAUX |
Contact Information
| Engineer | Kator,, Khaled; Lic. No.: C69781 | 19519 TULSA ST NORTHRIDGE, CA 91326 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/2/2023 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Rough | 2/2/2023 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 2/2/2023 | Approved | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Corrections Issued | THOMAS FINNILA |
| Deputy Reinf. Concrete | 2/9/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 2/13/2023 | Approved | ROBERT GOLD |
| Footing/Foundation/Slab | 2/13/2023 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/10/2023 | Conditional Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/10/2023 | Conditional Approval | RYAN SALAZAR |
| Green Building Rough | 4/10/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 4/10/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 4/10/2023 | Approved | RYAN SALAZAR |
| Wood Frame | 4/10/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/12/2023 | Partial Approval | RYAN SALAZAR |
| HVAC-Rough | 5/23/2023 | Partial Inspection | RYAN SALAZAR |
| Pre-Inspection | 5/23/2023 | Partial Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/20/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 2/20/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/20/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 2/28/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 3/4/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/4/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/8/2025 | Approved | RYAN SALAZAR |
| Final | 8/8/2025 | Partial Approval | RYAN SALAZAR |
| Green Building Final | 8/8/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 8/8/2025 | Approved | RYAN SALAZAR |
| Smoke Detectors | 8/8/2025 | Approved | RYAN SALAZAR |
| Final | 8/19/2025 | OK to Issue CofO | RYAN SALAZAR |