17417 W WEDDINGTON ST 91316
Certificate Information: 17417 W WEDDINGTON ST 91316
- Application / Permit
- 21010-20000-05080
- Plan Check / Job No.
- B21VN13269
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25' X 34'-3" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g) WITH ATTACHED 8' X 14' TRELLIS
- Permit Issued
- Issued on 11/9/2021
- Issuing Office
- Current Status
- CofO Issued on 9/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2021 | SELLA BENYAMIN |
| Corrections Issued | 10/5/2021 | SELLA BENYAMIN |
| Building Plans Picked Up | 10/8/2021 | APPLICANT |
| Issued | 11/9/2021 | APPLICANT |
| CofO in Progress | 8/12/2022 | SEAN HAUPT |
| Permit Finaled | 9/10/2022 | MICHAEL SMITH |
| CofO Issued | 9/10/2022 | MICHAEL SMITH |
| Permit Finaled | 9/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/19/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 10/29/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 11/8/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/11/2022 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 1/11/2022 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 1/11/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 1/14/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 1/14/2022 | Approved | SEAN HAUPT |
| Sewer | 1/27/2022 | Partial Inspection | JUSTIN HAWLEY |
| Sewer | 1/28/2022 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Approved | SEAN HAUPT |
| Special/Order Compliance | 2/16/2022 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 3/3/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 3/3/2022 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 3/3/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 3/17/2022 | Approved | SEAN HAUPT |
| Insulation | 3/29/2022 | Approved | SEAN HAUPT |
| Special/Order Compliance | 3/29/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 4/6/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/11/2022 | Approved | SEAN HAUPT |
| Special/Order Compliance | 4/11/2022 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/29/2022 | Approved | SEAN HAUPT |
| Final | 6/29/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 6/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 6/29/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 6/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 6/29/2022 | Approved | SEAN HAUPT |
| Final | 8/12/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 8/12/2022 | Approved | SEAN HAUPT |
| Service/Power Release | 8/12/2022 | Approved | SEAN HAUPT |