10349 N RINCON AVE 91331
Certificate Information: 10349 N RINCON AVE 91331
- Application / Permit
- 21010-20000-05077
- Plan Check / Job No.
- B21VN13255
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 19'9" X 25' ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2021 | PINANK PATEL |
| Corrections Issued | 10/8/2021 | PINANK PATEL |
| Plan Check Approved | 3/16/2022 | PINANK PATEL |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 10/27/2022 | MICHEL ABAJAN |
| Permit Finaled | 10/29/2022 | MICHAEL SMITH |
| CofO Issued | 10/29/2022 | MICHAEL SMITH |
| Permit Finaled | 10/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 10/19/2021 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 1/13/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 3/1/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/3/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/15/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/15/2022 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 4/15/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 4/15/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/2/2022 | Partial Approval | MICHEL ABAJAN |
| Insulation | 5/2/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 5/2/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/19/2022 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 5/19/2022 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Rough | 5/19/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 5/19/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/27/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/27/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/27/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/27/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 5/27/2022 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 5/27/2022 | Partial Inspection | MICHEL ABAJAN |
| Shower Pan | 5/27/2022 | Approved | MICHEL ABAJAN |
| Insulation | 6/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 6/13/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/13/2022 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 6/22/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/22/2022 | Approved | MICHEL ABAJAN |
| Sewer | 6/22/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 6/22/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 6/28/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/18/2022 | Approved | MICHEL ABAJAN |
| Final | 7/18/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/18/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/18/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/18/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 7/18/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 7/18/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/10/2022 | Approved | MICHEL ABAJAN |
| Final | 8/10/2022 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 8/10/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 8/10/2022 | Approved | MICHEL ABAJAN |
| Service/Power Release | 8/10/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 10/27/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 10/27/2022 | Approved | MICHEL ABAJAN |