7049 N GARDEN GROVE AVE 91335

Certificate Information: 7049 N GARDEN GROVE AVE 91335

Application / Permit
21010-20000-05074
Plan Check / Job No.
B21VN13237
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-2" X 46' DETACHED ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 12/7/2021
Issuing Office
Current Status
Issued on 12/7/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/29/2021 APPLICANT
Assigned to Plan Check Engineer 10/1/2021 SERGIO MUNIZ
Corrections Issued 10/3/2021 SERGIO MUNIZ
Plan Check Approved 12/6/2021 SERGIO MUNIZ
Issued 12/7/2021 APPLICANT
Building Plans Picked Up 12/9/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/12/2021 GABRIEL ROBLES
Sewer availability Cleared 10/12/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/13/2021 GABRIEL ROBLES
Low Impact Development Cleared 11/18/2021 TA ANH
Roof/Waste drainage to street Cleared 11/18/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/6/2024 Partial Approval HENRY KIM
Footing/Foundation/Slab 3/11/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 3/27/2024 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Partial Approval JEFFREY HARTLINE
Green Building Rough 3/27/2024 Not Ready for Inspection JEFFREY HARTLINE
Verify Sprinkler Sign Off 3/27/2024 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 Approved JEFFREY BULL
Rough-Elec/Plmb/HVAC 4/1/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 4/3/2024 Approved JEFFREY BULL
Shower Pan 4/3/2024 Approved JEFFREY BULL
Underground Mechanical 4/5/2024 Approved JEFFREY BULL
Insulation 4/9/2024 Corrections Issued JEFFREY BULL
Drywall Nailing 4/12/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 5/15/2024 Approved JEFFREY BULL
Final 5/15/2024 Corrections Issued JEFFREY BULL
Green Building Final 5/15/2024 Not Ready for Inspection JEFFREY BULL
Green Building Rough 5/15/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 5/15/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 5/15/2024 Approved JEFFREY BULL
Smoke Detectors 5/15/2024 Approved JEFFREY BULL
Verify Sprinkler Sign Off 5/15/2024 Approved JEFFREY BULL