8417 N SHIRLEY AVE 91324

Certificate Information: 8417 N SHIRLEY AVE 91324

Application / Permit
21010-20000-05068
Plan Check / Job No.
B21VN13191
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 30' X 30' DETACHED ONE-CAR GARAGE WITH STORAGE AND 30' X 6' ATTACHED PATIO COVER. WORK PER ENGINEER.
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
Issued on 4/25/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/28/2021 APPLICANT
Assigned to Plan Check Engineer 9/29/2021 ROSENDO MEDINA
Corrections Issued 10/2/2021 ROSENDO MEDINA
Applicant returned to address corrections 3/25/2022 LUISANGEL VALENZUELA
Plan Check Approved 4/18/2022 ROSENDO MEDINA
Building Plans Picked Up 4/18/2022 APPLICANT
Issued 4/25/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/5/2021 DAGOVERTO GUERRERO
ZA Case Cleared 10/15/2021 PABLO ESTRADA
Hydrant and Access approval Cleared 1/11/2022 GILBERT URREA
Low Impact Development Cleared 3/10/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 3/18/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Hamidzadeh,, Amir; Lic. No.: C68216 212 DIRT RD      LAKE SHERWOOD, CA 91361

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2022 Partial Approval JEFFREY PARD
Excavation/Setback/Form/Re-Bar 6/30/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 8/1/2022 Approved JEFFREY PARD
ELECTRICAL-Rough 8/1/2022 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 8/25/2022 Approved JEFFREY PARD
Drywall Nailing 10/18/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 1/17/2023 Partial Approval JOHN KIDWELL
Final 4/26/2023 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 4/26/2023 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 4/26/2023 SGSOV Not Required JOHN KIDWELL
Service/Power Release 4/26/2023 Not Required JOHN KIDWELL
Smoke Detectors 4/26/2023 Approved JOHN KIDWELL