445 E TERRILL AVE 90042
Certificate Information: 445 E TERRILL AVE 90042
- Application / Permit
- 21010-20000-05067
- Plan Check / Job No.
- B21VN13188
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2--STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)
- Permit Issued
- Issued on 1/18/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/2/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/9/2021 | STEVEN KIM |
| Building Plans Picked Up | 12/3/2021 | APPLICANT |
| Applicant returned to address corrections | 11/15/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 1/13/2023 | NILOOFAR MEHRAIN |
| Issued | 1/18/2023 | APPLICANT |
| CofO in Progress | 1/3/2024 | AMY COLIN |
| CofO Issued | 1/12/2024 | DEROLD HAUFF |
| Permit Finaled | 1/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2022 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 4/28/2022 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 4/28/2022 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 4/28/2022 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 4/28/2022 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 4/28/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 5/13/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 7/17/2022 | RUEL COLE |
| "D" conditions | Cleared | 8/1/2022 | DALIA MOKAYED |
| "Q" conditions | Cleared | 8/1/2022 | DALIA MOKAYED |
| ZI | Cleared | 8/1/2022 | DALIA MOKAYED |
| Low Impact Development | Cleared | 10/28/2022 | SARAH YOUSSEF |
| GPI Written Notices | Cleared | 11/15/2022 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 11/15/2022 | NILOOFAR MEHRAIN |
| Roof/Waste drainage to street | Cleared | 1/18/2023 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/12/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 7/6/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 7/28/2023 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Rough | 7/28/2023 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 7/28/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 7/28/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 8/14/2023 | Not Ready for Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 8/16/2023 | Approved | AMY COLIN |
| Insulation | 8/18/2023 | Approved | AMY COLIN |
| Drywall Nailing | 8/24/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 9/27/2023 | Corrections Issued | AMY COLIN |
| Final | 9/27/2023 | Corrections Issued | AMY COLIN |
| Green Building Final | 9/27/2023 | Approved | AMY COLIN |
| Green Building Rough | 9/27/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Not Ready | AMY COLIN |
| Service/Power Release | 9/27/2023 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 9/27/2023 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 9/27/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 10/10/2023 | Corrections Issued | AMY COLIN |
| Final | 10/18/2023 | Not Ready for Inspection | AMY COLIN |
| Reinforced Masonry Frame | 10/18/2023 | Partial Inspection | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 10/18/2023 | Approved | AMY COLIN |
| Final | 12/18/2023 | Partial Inspection | AMY COLIN |
| Reinforced Masonry Frame | 12/18/2023 | Approved | AMY COLIN |
| Final | 1/3/2024 | OK to Issue CofO | AMY COLIN |