6660 W MARYLAND DR 90048

Certificate Information: 6660 W MARYLAND DR 90048

Application / Permit
21010-20000-05066
Plan Check / Job No.
B21VN13186
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 21' X 22'-4" IRREGULAR SHAPED DETACHED GARAGE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/24/2022
Issuing Office
Current Status
CofO Issued on 2/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 RAPHAEL ROSAS
Corrections Issued 10/19/2021 RAPHAEL ROSAS
Quality Review Completed 10/28/2021 STEVEN KIM
Applicant returned to address corrections 2/11/2022 RAPHAEL ROSAS
Applicant returned to address corrections 3/2/2022 RAPHAEL ROSAS
Building Plans Picked Up 3/3/2022 APPLICANT
Plan Check Approved 3/24/2022 RAPHAEL ROSAS
Issued 3/24/2022 APPLICANT
CofO in Progress 1/30/2023 JEREMY TODD
Permit Finaled 2/8/2023 DANIEL ORRANTE
CofO Issued 2/8/2023 DANIEL ORRANTE
Permit Finaled 2/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

ZI Cleared 11/23/2021 MAXFIELD VERMY
Construction near power lines Cleared 12/9/2021 WALTER RAMIREZ
Low Impact Development Cleared 1/27/2022 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 1/28/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 1/28/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/31/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 3/31/2022 Partial Inspection EVAN COOPER
Footing/Foundation/Slab 4/7/2022 Approved EVAN COOPER
METHANE-Barrier 4/7/2022 Approved EVAN COOPER
METHANE-Subgrade 4/7/2022 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 6/21/2022 Corrections Issued KEVIN SARGSYAN
METHANE-Rough 6/21/2022 Corrections Issued KEVIN SARGSYAN
Special/Order Compliance 9/27/2022 Approved EVAN COOPER
Special/Order Compliance 9/29/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 1/18/2023 Approved JEREMY TODD
Drywall Nailing 1/18/2023 Approved JEREMY TODD
Final 1/18/2023 Not Ready for Inspection JEREMY TODD
METHANE-Final 1/18/2023 Approved JEREMY TODD
METHANE-Rough 1/18/2023 Approved JEREMY TODD
SGSOV-Seismic Gas S/O Valve 1/18/2023 SGSOV Approved JEREMY TODD
Service/Power Release 1/18/2023 Approved JEREMY TODD
Smoke Detectors 1/18/2023 Approved JEREMY TODD
Final 1/27/2023 OK to Issue CofO JEREMY TODD