17203 W HART ST 91406

Certificate Information: 17203 W HART ST 91406

Application / Permit
21010-20000-05046
Plan Check / Job No.
B21VN13160
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 18' X 30' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/15/2022
Issuing Office
Current Status
CofO Issued on 1/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2021 APPLICANT
Assigned to Plan Check Engineer 10/1/2021 RAPHAEL ROSAS
Corrections Issued 10/3/2021 RAPHAEL ROSAS
Building Plans Picked Up 4/5/2022 APPLICANT
Issued 4/15/2022 APPLICANT
CofO in Progress 12/14/2022 SEAN HAUPT
Permit Finaled 1/20/2023 JOHN JANSON
CofO Issued 1/20/2023 JOHN JANSON
Permit Finaled 1/20/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/14/2021 DAGOVERTO GUERRERO
Miscellaneous Cleared 10/14/2021 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 10/21/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 10/21/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 12/17/2021 MATTHEW CRAIG
Construction near power lines Cleared 1/21/2022 RIDWAN HARDY
Low Impact Development Cleared 3/16/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/23/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/19/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 5/5/2022 Approved SEAN HAUPT
Sewer 6/13/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 7/1/2022 Approved SEAN HAUPT
Green Building Rough 7/1/2022 Not Ready for Inspection SEAN HAUPT
Rough-Elec/Plmb/HVAC 7/1/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 7/1/2022 Approved SEAN HAUPT
Gas Test 7/15/2022 Approved SEAN HAUPT
Insulation 7/15/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 7/15/2022 Approved SEAN HAUPT
Shower Pan 7/15/2022 Approved SEAN HAUPT
Drywall Nailing 7/21/2022 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 11/29/2022 Approved SEAN HAUPT
Final 11/29/2022 Corrections Issued SEAN HAUPT
Gas Test 11/29/2022 Approved SEAN HAUPT
Green Building Final 11/29/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 11/29/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 11/29/2022 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 11/29/2022 Approved SEAN HAUPT
Final 12/13/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 12/13/2022 Approved SEAN HAUPT
Service/Power Release 12/13/2022 Not Required SEAN HAUPT