18341-18343 W TARZANA DR 91356

Certificate Information: 18341-18343 W TARZANA DR 91356

Application / Permit
21010-20000-05033
Plan Check / Job No.
B21VN13109
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*ePLAN CHECK* 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING FOR (N) ACCESSORY DWELLING PER LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 10/12/2022
Issuing Office
Current Status
CofO in Progress on 2/19/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/28/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 LAMAR DAVIS
Corrections Issued 11/1/2021 LAMAR DAVIS
Quality Review Completed 11/13/2021 HERNAN ARREOLA
Applicant returned to address corrections 4/6/2022 LAMAR DAVIS
Applicant returned to address corrections 7/26/2022 LAMAR DAVIS
Applicant returned to address corrections 8/3/2022 LAMAR DAVIS
Plan Check Approved 9/13/2022 LAMAR DAVIS
Issued 10/12/2022 APPLICANT
CofO in Progress 2/19/2026 JOHN KIDWELL

Permit Application Clearance Information

Address approval Cleared 11/8/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/8/2021 LEE GUILBEAUX
Sewer availability Cleared 11/15/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/9/2021 LEE GUILBEAUX
Grading Pre-Inspection Cleared 4/4/2022 VASIL MIHALEV
GPI Written Notices Cleared 7/26/2022 ALEXANDER ANDREWS

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/21/2023 Approved SEAN HAUPT
Deputy Drilled-In Anchors 12/1/2023 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 12/4/2023 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 12/4/2023 Not Ready for Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 12/12/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 12/12/2023 Approved SEAN HAUPT
Deputy Reinf. Concrete 12/13/2023 Approved JEFFREY PARD
Deputy Drilled-In Anchors 12/28/2023 Approved SEAN HAUPT
Deputy Wood Construction 1/16/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Corrections Issued JOHN KIDWELL
HVAC-Rough 3/11/2024 Partial Approval JOHN KIDWELL
PLUMBING-Rough 3/11/2024 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 4/11/2024 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 5/31/2024 Approved JOHN KIDWELL
Green Building Rough 5/31/2024 Approved JOHN KIDWELL
Insulation 5/31/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 5/31/2024 Partial Approval JOHN KIDWELL
Drywall Nailing 6/7/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 6/7/2024 Partial Approval JOHN KIDWELL
Shower Pan 6/12/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 8/9/2024 Approved JOHN KIDWELL
ELECTRICAL-Final 10/10/2024 Partial Inspection JOHN KIDWELL
ELECTRICAL-Final 7/1/2025 Approved JOHN KIDWELL
HVAC-Final 7/1/2025 Conditional Approval JOHN KIDWELL
PLUMBING-Final 7/1/2025 Approved JOHN KIDWELL
Service/Power Release 7/1/2025 Approved JOHN KIDWELL
Deputy Drilled-In Anchors 10/7/2025 Partial Approval SEAN WIRCH
Service/Power Release 10/8/2025 Approved SEAN WIRCH
Final 12/11/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 12/11/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Not Required JOHN KIDWELL
Smoke Detectors 12/11/2025 Approved JOHN KIDWELL
Final 1/5/2026 Not Ready for Inspection JOHN KIDWELL
Green Building Final 1/5/2026 Approved JOHN KIDWELL
Final 1/20/2026 OK to Issue CofO JOHN KIDWELL