10755 W BROOKVIEW DR 91602
Certificate Information: 10755 W BROOKVIEW DR 91602
- Application / Permit
- 21010-20000-05002
- Plan Check / Job No.
- B21VN13041
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW DETACHED 33' X 35'-9" IRREGULAR SHAPED GARAGE AND STORAGE PER ENGINEERING.
- Permit Issued
- Issued on 6/15/2022
- Issuing Office
- Current Status
- Issued on 6/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | COLIN LOREDO |
| Corrections Issued | 10/25/2021 | COLIN LOREDO |
| Quality Review Completed | 10/28/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 10/29/2021 | APPLICANT |
| Plan Check Approved | 4/19/2022 | COLIN LOREDO |
| Issued | 6/15/2022 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 11/8/2021 | LAUREN PADICK |
| Low Impact Development | Cleared | 4/5/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/25/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yamamoto,, Tozo; Lic. No.: C88646 | 6151 BECKETT STATION CT WEST CHESTER, OH 45069 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 9/30/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 10/14/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 4/17/2024 | Approved | JOHN HAYES |
| Insulation | 4/17/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 1/30/2025 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 1/30/2025 | Approved | JUAN VALENZUELA |
| Final | 1/30/2025 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 1/30/2025 | Approved | JUAN VALENZUELA |
| Green Building Rough | 1/30/2025 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 1/30/2025 | SGSOV Approved | JUAN VALENZUELA |
| Structural Steel Frame | 1/30/2025 | Approved | JUAN VALENZUELA |
| Final | 2/13/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |