2010 N STRADELLA ROAD 90077

Certificate Information: 2010 N STRADELLA ROAD 90077

Application / Permit
21010-20000-04997
Plan Check / Job No.
B21VN13017
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 2/27/2024
Issuing Office
West Los Angeles
Current Status
Issued on 2/27/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/24/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 NILOOFAR MEHRAIN
Corrections Issued 10/12/2021 NILOOFAR MEHRAIN
Quality Review Completed 10/15/2021 STEVEN KIM
Building Plans Picked Up 10/18/2021 APPLICANT
Applicant returned to address corrections 7/12/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/10/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/26/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/25/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/20/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/10/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/2/2023 NILOOFAR MEHRAIN
Plan Check Approved 5/5/2023 NILOOFAR MEHRAIN
Issued 2/27/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/29/2021 NIKTA MOUSAVI
BHO/Hillside ordinance Cleared 10/29/2021 NIKTA MOUSAVI
BHO/Hillside ordinance Cleared 10/29/2021 NIKTA MOUSAVI
BHO/Hillside ordinance Cleared 10/29/2021 NIKTA MOUSAVI
BHO/Hillside ordinance Cleared 10/29/2021 NIKTA MOUSAVI
BHO/Hillside ordinance Cleared 10/29/2021 NIKTA MOUSAVI
Trees in Parkway Cleared 11/9/2021 ADALBERTO VERA
Eng Process Fee Ord 176,300 Cleared 11/16/2021 NIKTA MOUSAVI
Sewer availability Cleared 11/16/2021 NIKTA MOUSAVI
Hydrant and Access approval Cleared 1/24/2022 KURT CORRAL
Permit Cleared 10/12/2022 NIKTA MOUSAVI
Low Impact Development Cleared 10/25/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 11/2/2022 NIKTA MOUSAVI
GPI Written Notices Cleared 12/20/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 12/20/2022 NILOOFAR MEHRAIN
Excavation more than 5-ft deep Cleared 5/2/2023 CALOSHA APPROVED

Contact Information

Contractor Boswell Construction Inc; Lic. No.: 934480-B 14611 VENTURA BLVD 2ND FLOOR      SHERMAN OAKS, CA 91403
Engineer Garza,, Omar Leonel; Lic. No.: S5593 600 WILSHIRE BLVD 760      LOS ANGELES, CA 90017

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Excavation/Setback/Form/Re-Bar 6/8/2026   

Inspection Request History

Deputy Reinf. Concrete 7/23/2024 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 7/24/2024 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/25/2024 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 8/1/2024 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 8/20/2024 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 9/5/2024 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 9/26/2024 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 10/8/2024 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 10/23/2024 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 11/22/2024 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 11/22/2024 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 11/26/2024 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/26/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/10/2025 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/29/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/29/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/29/2025 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 5/29/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 6/12/2025 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 7/2/2025 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/31/2025 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 7/31/2025 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 8/13/2025 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 8/13/2025 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/5/2025 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/15/2025 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/16/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/29/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/3/2025 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/29/2025 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 11/3/2025 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 12/4/2025 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/30/2025 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 2/4/2026 Not Ready for Inspection CHRISTOPHER WILSON
Gas Test 2/4/2026 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 2/4/2026 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 2/9/2026 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/9/2026 Partial Approval CARLOS MATAMOROS
Gas Test 2/9/2026 Partial Approval CARLOS MATAMOROS
Sewer 2/9/2026 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 2/18/2026 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 2/18/2026 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/24/2026 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/24/2026 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/13/2026 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 3/18/2026 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/26/2026 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/15/2026 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/28/2026 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/7/2026 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 5/14/2026 Partial Approval RYAN SALAZAR
Gas Test 5/27/2026 Partial Approval RYAN SALAZAR
PLUMBING-Rough 5/27/2026 Partial Approval RYAN SALAZAR
Sewer 5/27/2026 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 5/29/2026 Not Ready for Inspection RYAN SALAZAR