22644 W SYLVAN ST 91367

Certificate Information: 22644 W SYLVAN ST 91367

Application / Permit
21010-20000-04993
Plan Check / Job No.
B21VN13005
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 2-STORY REC. ROOM
Permit Issued
Issued on 9/17/2024
Issuing Office
Valley
Current Status
CofO in Progress on 4/9/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/24/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 SELLA BENYAMIN
Corrections Issued 10/28/2021 SELLA BENYAMIN
Quality Review Completed 11/4/2021 STEVEN KIM
Building Plans Picked Up 11/5/2021 APPLICANT
Applicant returned to address corrections 1/10/2023 SELLA BENYAMIN
Plan Check Approved 9/17/2024 SELLA BENYAMIN
Issued 9/17/2024 APPLICANT
CofO in Progress 4/9/2026 TROY SANDERS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/10/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 2/17/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/11/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/21/2025 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Approval TROY SANDERS
Green Building Rough 2/28/2025 Not Ready for Inspection TROY SANDERS
Verify Sprinkler Sign Off 2/28/2025 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 4/1/2025 Not Ready for Inspection TROY SANDERS
Final 4/1/2025 Not Ready for Inspection TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Partial Approval TROY SANDERS
Footing/Foundation/Slab 4/1/2025 Approved TROY SANDERS
Green Building Final 4/1/2025 Not Ready for Inspection TROY SANDERS
Green Building Rough 4/1/2025 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 4/1/2025 SGSOV Not Ready TROY SANDERS
Service/Power Release 4/1/2025 Not Ready for Inspection TROY SANDERS
Smoke Detectors 4/1/2025 Not Ready for Inspection TROY SANDERS
Verify Sprinkler Sign Off 4/1/2025 Approved TROY SANDERS
BUILDING-Rough-Frame 3/5/2026 Not Ready for Inspection TROY SANDERS
Final 3/5/2026 Not Ready for Inspection TROY SANDERS
Green Building Final 3/5/2026 Not Ready for Inspection TROY SANDERS
Green Building Rough 3/5/2026 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Approved TROY SANDERS
Service/Power Release 3/5/2026 Approved TROY SANDERS
Smoke Detectors 3/5/2026 Not Ready for Inspection TROY SANDERS
Rough-Elec/Plmb/HVAC 3/17/2026 Approved TROY SANDERS
BUILDING-Rough-Frame 4/8/2026 Approved TROY SANDERS
Final 4/8/2026 OK to Issue CofO TROY SANDERS
Green Building Final 4/8/2026 Approved TROY SANDERS
Smoke Detectors 4/8/2026 Approved TROY SANDERS
Special/Order Compliance 5/26/2026 Corrections Issued TROY SANDERS