15149 W WEDDINGTON ST 91411
Certificate Information: 15149 W WEDDINGTON ST 91411
- Application / Permit
- 21010-20000-04932
- Plan Check / Job No.
- B21VN12882
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 90'-8" X 46' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND BASEMENT; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- CofO Issued on 10/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | SELLA BENYAMIN |
| Corrections Issued | 10/13/2021 | SELLA BENYAMIN |
| Quality Review Completed | 10/15/2021 | STEVEN KIM |
| Building Plans Picked Up | 12/16/2021 | APPLICANT |
| Applicant returned to address corrections | 12/21/2021 | SELLA BENYAMIN |
| Plan Check Approved | 1/7/2022 | SELLA BENYAMIN |
| Issued | 1/11/2022 | APPLICANT |
| CofO in Progress | 8/30/2024 | JACK KARGODORIAN |
| CofO Issued | 10/7/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/7/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/24/2021 | ROBERT DUFF |
| Permit | Cleared | 11/2/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/2/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 12/1/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/6/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/1/2022 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/7/2022 | Corrections Issued | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 2/8/2022 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 2/8/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 2/9/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/14/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 2/17/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 2/24/2022 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 2/24/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Shotcrete | 2/28/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 3/25/2022 | Conditional Approval | DAVID MATSON |
| Deck | 3/29/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 3/31/2022 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 4/20/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 4/26/2022 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 4/26/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2022 | Conditional Approval | JACK KARGODORIAN |
| Underground Mechanical | 9/16/2022 | Partial Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/12/2022 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Conditional Approval | THOMAS FINNILA |
| Structural Steel Frame | 10/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 10/25/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 10/25/2022 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/7/2022 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 11/7/2022 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/7/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 11/7/2022 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 11/16/2022 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/21/2022 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 11/21/2022 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/21/2022 | Partial Approval | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 11/21/2022 | Partial Approval | THOMAS FINNILA |
| Insulation | 11/30/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 11/30/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 12/8/2022 | Partial Approval | MISAEL ESPARZA |
| Underground Mechanical | 12/21/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 12/22/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 12/22/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 12/23/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 12/23/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 12/28/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Conditional Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 2/8/2023 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 2/21/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 2/22/2023 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/6/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 3/6/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/6/2023 | Partial Approval | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 3/6/2023 | Approved | MICHEL ABAJAN |
| Insulation | 3/10/2023 | Conditional Approval | THOMAS FINNILA |
| Drywall Nailing | 3/15/2023 | Approved | THOMAS FINNILA |
| Shower Pan | 8/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 8/25/2023 | Corrections Issued | THOMAS FINNILA |
| Shower Pan | 8/30/2023 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/6/2023 | No Access for Inspection | THOMAS FINNILA |
| HVAC-Rough | 9/6/2023 | No Access for Inspection | THOMAS FINNILA |
| Pre-Inspection | 10/19/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/25/2023 | Approved | THOMAS FINNILA |
| Shower Pan | 10/25/2023 | Approved | THOMAS FINNILA |
| Underground Mechanical | 12/28/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Underground Mechanical | 4/22/2024 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/10/2024 | Approved | JACK KARGODORIAN |
| Final | 6/10/2024 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/10/2024 | Approved | JACK KARGODORIAN |
| Green Building Final | 6/10/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Not Ready | JACK KARGODORIAN |
| Service/Power Release | 6/10/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 6/10/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Final | 6/28/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Final | 7/15/2024 | Partial Approval | JACK KARGODORIAN |
| HVAC-Final | 7/18/2024 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 7/18/2024 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 7/19/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 7/19/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 7/24/2024 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 7/30/2024 | Approved | JACK KARGODORIAN |
| Service/Power Release | 7/31/2024 | Approved | JACK KARGODORIAN |
| Final | 8/21/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 8/21/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 8/21/2024 | Approved | JACK KARGODORIAN |
| Final | 8/30/2024 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 8/30/2024 | Approved | JACK KARGODORIAN |