11948 W BLYTHE ST 91605

Certificate Information: 11948 W BLYTHE ST 91605

Application / Permit
21010-20000-04921
Plan Check / Job No.
B21VN12854
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 27'-2" X 27'-3" IRREGULAR SHAPED (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
CofO in Progress on 1/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/22/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 SELLA BENYAMIN
Corrections Issued 10/19/2021 SELLA BENYAMIN
Quality Review Completed 10/21/2021 STEVEN KIM
Building Plans Picked Up 10/25/2021 APPLICANT
Plan Check Approved 4/5/2022 SELLA BENYAMIN
Issued 4/5/2022 APPLICANT
CofO in Progress 1/5/2026 MATTHEW NELSON

Permit Application Clearance Information

Address approval Cleared 10/25/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 10/26/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 10/26/2021 JOSE DUARTE-DIAZ
Construction near power lines Cleared 2/18/2022 RIDWAN HARDY
Low Impact Development Cleared 3/21/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 3/21/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/18/2022 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 9/28/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 10/10/2023 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 11/22/2023 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Approved MATTHEW NELSON
PLUMBING-Rough 11/29/2023 Approved MATTHEW NELSON
ELECTRICAL-Rough 12/15/2023 Approved MATTHEW NELSON
HVAC-Rough 12/15/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/15/2023 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 12/28/2023 Approved MATTHEW NELSON
Green Building Rough 12/28/2023 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 12/28/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/8/2024 Corrections Issued MATTHEW NELSON
Insulation 1/11/2024 Approved THOMAS FINNILA
Interior/Exterior Lathing 1/16/2024 Approved MATTHEW NELSON
Drywall Nailing 1/19/2024 Approved MATTHEW NELSON
Pre-Inspection 2/13/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/4/2024 Approved MATTHEW NELSON
Shower Pan 3/4/2024 Approved MATTHEW NELSON
Pre-Inspection 5/31/2024 Partial Inspection MATTHEW NELSON
Service/Power Release 12/11/2024 Corrections Issued MATTHEW NELSON
Final 4/29/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Final 4/29/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Service/Power Release 4/29/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 4/29/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Service/Power Release 8/25/2025 Partial Approval MATTHEW NELSON
Final 12/23/2025 Corrections Issued CRAIG DAVIS
Green Building Final 12/23/2025 Approved CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Not Ready CRAIG DAVIS
Service/Power Release 12/23/2025 Not Ready for Inspection CRAIG DAVIS
Smoke Detectors 12/23/2025 Not Ready for Inspection CRAIG DAVIS
Final 12/30/2025 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Approved MATTHEW NELSON
Service/Power Release 12/30/2025 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 12/30/2025 Approved MATTHEW NELSON
Final 1/2/2026 OK to Issue CofO MATTHEW NELSON
Service/Power Release 1/2/2026 Approved MATTHEW NELSON