8438 N MATILIJA AVE 91402
Certificate Information: 8438 N MATILIJA AVE 91402
- Application / Permit
- 21010-20000-04897
- Plan Check / Job No.
- B21VN12813
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: (N) 18' x 30' ADU PER Ordinance 186481
- Permit Issued
- Issued on 6/4/2022
- Issuing Office
- Current Status
- CofO Issued on 12/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2021 | HERNAN ARREOLA |
| Corrections Issued | 9/26/2021 | HERNAN ARREOLA |
| Plan Check Approved | 5/31/2022 | HERNAN ARREOLA |
| Issued | 6/4/2022 | APPLICANT |
| CofO in Progress | 10/13/2023 | GREGG CUMMINGS |
| Permit Finaled | 12/12/2023 | RUBEN SALAS |
| CofO Issued | 12/12/2023 | RUBEN SALAS |
| Permit Finaled | 12/12/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/18/2022 | RIDWAN HARDY |
| Address approval | Cleared | 2/22/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/23/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 5/16/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/19/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/26/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 8/1/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/4/2022 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/17/2022 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 10/5/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/13/2022 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 10/13/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/28/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 11/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 11/28/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 11/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 11/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 11/28/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/6/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/6/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 12/6/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 12/6/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/12/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/22/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/22/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 12/22/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 12/22/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 12/28/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/30/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/30/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 12/30/2022 | Approved | GREGG CUMMINGS |
| Insulation | 12/30/2022 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 1/12/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 1/18/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/18/2023 | Partial Approval | GREGG CUMMINGS |
| Service/Power Release | 2/8/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Sewer | 2/8/2023 | Approved | GREGG CUMMINGS |
| Shower Pan | 2/8/2023 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 2/8/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 2/8/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 2/13/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/8/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/14/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/15/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Final | 5/15/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 5/15/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 5/15/2023 | Approved | GREGG CUMMINGS |
| HVAC-Final | 5/15/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 5/15/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 5/15/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 5/15/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/12/2023 | Approved | GREGG CUMMINGS |
| Final | 10/12/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 10/12/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 10/12/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 10/12/2023 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 10/12/2023 | Approved | GREGG CUMMINGS |