1240 1/2 N NEPTUNE AVE 90744
Certificate Information: 1240 1/2 N NEPTUNE AVE 90744
- Application / Permit
- 21010-20000-04880
- Plan Check / Job No.
- B21VN12779
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (35'-8"x22'-0") 800 SQ. FT. DETACHED ACCESSORY DWELLING UNIT. USING WFPP PER GCS 65852.2 (e)(1)(B) & LAMC 12.22A.33(c), (d), & (g).
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2021 | PETER MOSESIAN |
| Corrections Issued | 9/28/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 9/30/2021 | APPLICANT |
| Applicant returned to address corrections | 11/9/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 11/22/2022 | HAYATO TSUCHIYA |
| Issued | 12/13/2022 | APPLICANT |
| CofO in Progress | 5/21/2024 | EUGENE CASSIDY |
| Permit Finaled | 5/21/2024 | ANSON MAGLASANG |
| CofO Issued | 5/21/2024 | ANSON MAGLASANG |
| Permit Finaled | 5/21/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 11/12/2021 | JOSE HERNANDEZ |
| Clean Up Green Up | Cleared | 11/15/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 11/15/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 11/15/2021 | DANIEL CORONADO |
| ZI | Cleared | 11/15/2021 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 4/29/2022 | MICHAEL GILLISSIE |
| Low Impact Development | Cleared | 6/22/2022 | ANTHONY VARGAS |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2022 | HUGO LOPEZ |
| Roof/Waste drainage to street | Cleared | 6/27/2022 | HUGO LOPEZ |
| Sewer availability | Cleared | 8/31/2022 | HUGO LOPEZ |
| Abandoned oil well | Cleared | 11/2/2022 | ROBERT DUFF |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/6/2023 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 3/22/2023 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/22/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 3/22/2023 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 3/22/2023 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 3/28/2023 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/28/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/19/2023 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 4/19/2023 | Partial Approval | EUGENE CASSIDY |
| Insulation | 4/24/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/27/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Gas Test | 6/27/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 6/27/2023 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 6/27/2023 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 6/27/2023 | Approved | EUGENE CASSIDY |
| Sewer | 6/27/2023 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 6/27/2023 | Approved | EUGENE CASSIDY |
| Insulation | 7/10/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/18/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/18/2023 | Partial Approval | EUGENE CASSIDY |
| Shower Pan | 7/18/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/25/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/29/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/29/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 11/29/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 11/29/2023 | Approved | EUGENE CASSIDY |
| HVAC-Final | 11/29/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 11/29/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 11/29/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 11/29/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/20/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 12/20/2023 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 12/20/2023 | Approved | EUGENE CASSIDY |
| HVAC-Final | 12/20/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 12/20/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Gas Company | EUGENE CASSIDY |
| Service/Power Release | 12/20/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 12/20/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/2/2024 | Approved | EUGENE CASSIDY |
| Final | 2/2/2024 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 2/2/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/21/2024 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 2/21/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 4/1/2024 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 4/1/2024 | Not Required | EUGENE CASSIDY |
| Final | 5/13/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/20/2024 | OK to Issue CofO | EUGENE CASSIDY |