363 S BUNDY DR 90049
Certificate Information: 363 S BUNDY DR 90049
- Application / Permit
- 21010-20000-04864
- Plan Check / Job No.
- B21VN12730
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRREGULAR 20'10" x 29'7" TWO-STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). NFPA-13D REQUIRED THROUGHOUT. SEE COMMENTS.
- Permit Issued
- Issued on 3/25/2022
- Issuing Office
- Current Status
- CofO Issued on 8/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | LUIS RINCON |
| Corrections Issued | 10/2/2021 | LUIS RINCON |
| Quality Review Completed | 10/8/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/9/2022 | LUIS RINCON |
| Plan Check Approved | 3/15/2022 | LUIS RINCON |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| Issued | 3/25/2022 | APPLICANT |
| CofO in Progress | 7/28/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 8/2/2023 | DANIEL ORRANTE |
| CofO Issued | 8/2/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/2/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2021 | DINAH GARIN |
| Sewer availability | Cleared | 11/2/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 12/4/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/20/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/20/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 1/25/2022 | KURT CORRAL |
Contact Information
| Contractor | Lush Remodeling Corporation; Lic. No.: 1073605-B | 555 SOUTH BARRINGTON AVE #226 LOS ANGELES, CA 90049 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/6/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 5/6/2022 | Partial Approval | JOHN KIDWELL |
| Sewer | 5/6/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/10/2022 | Partial Approval | JOHN KIDWELL |
| Masonry Wall/Backfill | 5/26/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/7/2022 | Corrections Issued | MICHAEL PELHAM |
| Verify Sprinkler Sign Off | 7/7/2022 | Corrections Issued | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 7/15/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/18/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/18/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 7/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/26/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/26/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 7/26/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 7/26/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 7/26/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/28/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 7/28/2022 | Approved | CARLOS MATAMOROS |
| Insulation | 8/4/2022 | Approved | KEVIN SARGSYAN |
| Shower Pan | 8/4/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 8/9/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/9/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Drywall Nailing | 8/11/2022 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/11/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 12/27/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 12/27/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Smoke Detectors | 12/27/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 1/25/2023 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 1/25/2023 | No Access for Inspection | CLAYTON GRAHAM |
| Final | 1/25/2023 | No Access for Inspection | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 1/25/2023 | No Access for Inspection | CLAYTON GRAHAM |
| Green Building Final | 1/25/2023 | No Access for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 1/25/2023 | No Access for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 1/25/2023 | No Access for Inspection | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 1/25/2023 | SGSOV Not Ready | CLAYTON GRAHAM |
| Service/Power Release | 1/25/2023 | No Access for Inspection | CLAYTON GRAHAM |
| Smoke Detectors | 1/25/2023 | No Access for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 2/1/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 2/1/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 2/1/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 2/1/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 2/7/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 2/7/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/7/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 2/7/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 2/7/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 2/17/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 2/17/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 2/28/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Special/Order Compliance | 3/2/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 7/28/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Service/Power Release | 7/28/2023 | Approved | OGANES TARAKHCHYAN |