12850 W ADMIRAL AVE 90066

Certificate Information: 12850 W ADMIRAL AVE 90066

Application / Permit
21010-20000-04855
Plan Check / Job No.
B21VN12659
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 36'-6" X 50'-8" IRREGULAR SHAPED 2-STORY SFD W/ ATTACHED GARAGE. ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 7/13/2022
Issuing Office
Current Status
CofO Issued on 11/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 RAPHAEL ROSAS
Corrections Issued 10/5/2021 RAPHAEL ROSAS
Quality Review Completed 10/13/2021 STEVEN KIM
Applicant returned to address corrections 5/3/2022 RAPHAEL ROSAS
Applicant returned to address corrections 6/7/2022 RAPHAEL ROSAS
Plan Check Approved 6/21/2022 RAPHAEL ROSAS
Issued 7/13/2022 APPLICANT
CofO in Progress 11/2/2023 HERBERT GIRON
Permit Finaled 11/8/2023 DANIEL ORRANTE
CofO Issued 11/8/2023 DANIEL ORRANTE
Permit Finaled 11/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/22/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 11/23/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 11/23/2021 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 2/14/2022 JOHN CONNEALLY
Low Impact Development Cleared 3/10/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/31/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor G N K Contruction; Lic. No.: 1052060-B 6618 SMOKETREE AVE      OAK PARK, CA 91377
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/25/2022 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 8/2/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/11/2022 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 10/18/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Partial Approval HERBERT GIRON
PLUMBING-Rough 10/18/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Corrections Issued HERBERT GIRON
HVAC-Rough 11/7/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Approved HERBERT GIRON
Deputy Wood Construction 11/21/2022 Conditional Approval HERBERT GIRON
Interior/Exterior Lathing 12/13/2022 Partial Approval RICHARD STEINBACH
BUILDING-Rough-Frame 12/15/2022 Approved HERBERT GIRON
Green Building Rough 12/15/2022 Approved HERBERT GIRON
METHANE-Rough 12/15/2022 Approved HERBERT GIRON
Verify Sprinkler Sign Off 12/15/2022 Approved HERBERT GIRON
Insulation 2/6/2023 Approved HERBERT GIRON
Drywall Nailing 2/15/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 2/15/2023 Approved HERBERT GIRON
Shower Pan 2/15/2023 Approved HERBERT GIRON
Underground Mechanical 5/22/2023 Corrections Issued HERBERT GIRON
Sewer 5/30/2023 Approved HERBERT GIRON
Underground Mechanical 5/30/2023 Approved HERBERT GIRON
Underground Mechanical 6/2/2023 Approved HERBERT GIRON
Gas Test 6/7/2023 Approved HERBERT GIRON
ELECTRICAL-Final 10/2/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 10/2/2023 Approved HERBERT GIRON
Green Building Final 10/2/2023 Corrections Issued HERBERT GIRON
METHANE-Barrier 10/2/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 10/2/2023 SGSOV Approved HERBERT GIRON
Service/Power Release 10/2/2023 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 10/2/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 10/6/2023 Corrections Issued HERBERT GIRON
Green Building Final 10/6/2023 Approved HERBERT GIRON
HVAC-Final 10/6/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 10/6/2023 Corrections Issued HERBERT GIRON
Service/Power Release 10/6/2023 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 10/6/2023 Approved HERBERT GIRON
ELECTRICAL-Final 10/24/2023 Approved HERBERT GIRON
Final 10/24/2023 Corrections Issued HERBERT GIRON
HVAC-Final 10/24/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 10/24/2023 Approved HERBERT GIRON
Service/Power Release 10/24/2023 Not Ready for Inspection HERBERT GIRON
Final 11/1/2023 OK to Issue CofO HERBERT GIRON
HVAC-Final 11/1/2023 Approved HERBERT GIRON
Service/Power Release 11/1/2023 Approved HERBERT GIRON