10808 W SARAH ST 91602
Certificate Information: 10808 W SARAH ST 91602
- Application / Permit
- 21010-20000-04801
- Plan Check / Job No.
- B21VN12537
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 41' X 13'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEER. "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
- Permit Issued
- Issued on 11/18/2021
- Issuing Office
- Current Status
- CofO Issued on 7/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | ROSENDO MEDINA |
| Corrections Issued | 10/6/2021 | ROSENDO MEDINA |
| Quality Review Completed | 10/8/2021 | STEVEN KIM |
| Applicant returned to address corrections | 10/27/2021 | ROSENDO MEDINA |
| Plan Check Approved | 11/9/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| Issued | 11/18/2021 | APPLICANT |
| CofO in Progress | 6/28/2023 | THOMAS FINNILA |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
| CofO Issued | 7/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/14/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 10/14/2021 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 11/3/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Construction Simon; Lic. No.: 996338-B | 12519 MARTHA STREET VALLEY VILLAGE, CA 91607 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/15/2022 | Conditional Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/22/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/25/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/2/2022 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/5/2022 | Approved | THOMAS FINNILA |
| Deputy Reinf. Concrete | 5/9/2022 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 8/30/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Green Building Rough | 8/30/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| MERV13>=Rough | 8/30/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| PLUMBING-Rough | 8/30/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 9/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/20/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 9/20/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/20/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 9/20/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/30/2022 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 10/19/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 10/20/2022 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Partial Approval | JACK KARGODORIAN |
| Insulation | 11/10/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 11/29/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Drywall Nailing | 12/2/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/26/2023 | Approved | JOHN COLEMAN |
| Final | 5/26/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 5/26/2023 | Approved | JOHN COLEMAN |
| Green Building Final | 5/26/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Rough | 5/26/2023 | Approved | JOHN COLEMAN |
| MERV13>=Final | 5/26/2023 | Approved | JOHN COLEMAN |
| MERV13>=Rough | 5/26/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 5/26/2023 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 5/26/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 5/26/2023 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 5/26/2023 | Approved | JOHN COLEMAN |
| Final | 6/6/2023 | Corrections Issued | JACK KARGODORIAN |
| Final | 6/12/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Final | 6/12/2023 | Approved | JACK KARGODORIAN |
| Service/Power Release | 6/12/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 6/27/2023 | OK to Issue CofO | THOMAS FINNILA |
| Service/Power Release | 6/27/2023 | Approved | THOMAS FINNILA |