2614 S CENTRAL AVE 90011

Certificate Information: 2614 S CENTRAL AVE 90011

Application / Permit
21010-20000-04790
Plan Check / Job No.
B21VN12491
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
NEW 120'-0" X 42'-9" 2-STORY OFFICE WITH PARKING GARAGE ON 1ST LEVEL
Permit Issued
Issued on 6/17/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2021 APPLICANT
Green Plans Picked Up 10/1/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 MARVEL DELACRUZ
Corrections Issued 10/22/2021 MARVEL DELACRUZ
Quality Review Completed 11/2/2021 STEVEN KIM
Building Plans Picked Up 11/4/2021 APPLICANT
Applicant returned to address corrections 2/11/2022 MARVEL DELACRUZ
Applicant returned to address corrections 4/13/2022 RAPHAEL ROSAS
Applicant returned to address corrections 5/3/2022 RAPHAEL ROSAS
Applicant returned to address corrections 5/23/2022 RAPHAEL ROSAS
Disabled Access Plans Picked Up 5/26/2022 APPLICANT
Applicant returned to address corrections 6/2/2022 RAPHAEL ROSAS
Plan Check Approved 6/6/2022 RAPHAEL ROSAS
Issued 6/17/2022 APPLICANT
CofO in Progress 5/31/2024 JAMES POWERS
Permit Finaled 5/31/2024 RAFAEL ESPINOZA
CofO Issued 5/31/2024 RAFAEL ESPINOZA
Permit Finaled 5/31/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Low Impact Development Cleared 11/10/2021 MARTIN FRAGOSO
Address approval Cleared 12/7/2021 JEANETTE VONG
Miscellaneous Cleared 12/7/2021 ANACANY HURTADO
Roof/Waste drainage to street Cleared 12/7/2021 JEANETTE VONG
Work Adjacent to Public Way Cleared 12/9/2021 ARMEN SARKISIAN
Green Code Cleared 2/2/2022 MICHAEL AYERS
Highway dedication Cleared 2/2/2022 JEANETTE VONG
Permit Cleared 2/2/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/10/2022 JEANETTE VONG
Sewer availability Cleared 2/10/2022 JEANETTE VONG
Trees in Parkway Cleared 2/16/2022 ADALBERTO VERA
Driveway location Cleared 2/17/2022 COLLINS ALLAN
Hydrant and Access approval Cleared 3/2/2022 KURT CORRAL
"D" conditions Cleared 3/29/2022 HELEN JADALI
Community Plan Implem. Overlay Cleared 3/29/2022 HELEN JADALI
Construction near power lines Cleared 3/31/2022 RIDWAN HARDY
Construction within easement Cleared 3/31/2022 RIDWAN HARDY
Redevelopment Project Area Cleared 4/26/2022 GRACIELA ACOSTA
ZI Cleared 4/26/2022 GRACIELA ACOSTA
DAS Clearance Cleared 5/5/2022 OLLIE CARTER

Contact Information

Contractor Delta General Contracting Inc; Lic. No.: 618245-B 4408 ALFARENA PLACE      TARZANA, CA 91356
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2022 Off-Hour Fees Due
Footing/Foundation/Slab 6/18/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 7/11/2022 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 7/11/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 7/11/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 7/12/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/14/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/29/2022 Conditional Approval WINSTON DUNNING
Masonry Wall/Backfill 7/29/2022 Not Ready for Inspection JAMES POWERS
Masonry Wall/Backfill 8/1/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/18/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/18/2022 Partial Approval JAMES POWERS
Deputy Other (see comments) 8/23/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/23/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 9/6/2022 Partial Approval JAMES POWERS
Masonry Wall/Backfill 9/6/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/21/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 9/21/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 10/17/2022 Partial Approval JAMES POWERS
Masonry Wall/Backfill 10/17/2022 Partial Approval JAMES POWERS
Deputy Other (see comments) 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Partial Approval JAMES POWERS
Wood Frame 11/23/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/23/2023 Partial Approval JAMES POWERS
Wood Frame 2/15/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 2/27/2023 Conditional Approval MICHAEL ROSENBERG
Wood Frame 4/21/2023 Approved LARRY ARNICK
Drywall Nailing 5/18/2023 Approved JAMES POWERS
Final 3/12/2024 Not Ready for Inspection JAMES POWERS
Green Building Final 4/10/2024 Approved JAMES POWERS
Final 5/28/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 5/28/2024 Approved JAMES POWERS
Green Building Rough 5/28/2024 Approved JAMES POWERS
Reinforced Masonry Frame 5/28/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV No Gas JAMES POWERS
Smoke Detectors 5/28/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 5/28/2024 Approved JAMES POWERS
Final 5/31/2024 OK to Issue CofO JAMES POWERS