1449 S DURANGO AVE 90035
Certificate Information: 1449 S DURANGO AVE 90035
- Application / Permit
- 21010-20000-04783
- Plan Check / Job No.
- B21VN12467
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED TWO-STORY (37' x 31'11", (1098.38 SQFT) FOR TWO ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(D) and applicable parts of LAMC 12.22 A.33 (c)-(d), (g)). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 7/25/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | PARISA ZAHABI |
| Corrections Issued | 9/25/2021 | PARISA ZAHABI |
| Quality Review Completed | 9/28/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 12/1/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 12/2/2021 | APPLICANT |
| Plan Check Approved | 3/17/2022 | PETER MOSESIAN |
| Issued | 7/25/2022 | APPLICANT |
| CofO in Progress | 6/29/2023 | JEREMY TODD |
| Permit Finaled | 7/10/2023 | DANIEL ORRANTE |
| CofO Issued | 7/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/9/2021 | RIDWAN HARDY |
| Address approval | Cleared | 2/22/2022 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2022 | TRACY TATE |
| Sewer availability | Cleared | 2/22/2022 | TRACY TATE |
| Low Impact Development | Cleared | 3/4/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/9/2022 | TRACY TATE |
| Grading Pre-Inspection | Cleared | 3/11/2022 | PARISA ZAHABI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hoerner,, John Brent; Lic. No.: S2145 | 24024 VIA CANDELA VALENCIA, CA 91355 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/1/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 9/6/2022 | Partial Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 11/14/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/16/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Barrier | 11/16/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 11/16/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 1/12/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 1/30/2023 | Corrections Issued | JEREMY TODD |
| ELECTRICAL-Rough | 1/30/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Corrections Issued | JEREMY TODD |
| Green Building Rough | 1/30/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 1/30/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Rough | 1/30/2023 | Approved | JEREMY TODD |
| Verify Sprinkler Sign Off | 1/30/2023 | Conditional Approval | JEREMY TODD |
| Deputy Wood Construction | 2/2/2023 | No Access for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 2/6/2023 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/6/2023 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 2/6/2023 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 2/6/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 2/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 2/13/2023 | Partial Approval | CLAYTON GRAHAM |
| Insulation | 2/27/2023 | Corrections Issued | JEREMY TODD |
| Interior/Exterior Lathing | 3/6/2023 | Approved | JEREMY TODD |
| Underground Mechanical | 4/13/2023 | Approved | JEREMY TODD |
| Masonry Wall/Backfill | 4/21/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 6/23/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 6/23/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 6/23/2023 | Approved | JEREMY TODD |
| Final | 6/23/2023 | Partial Inspection | JEREMY TODD |
| Green Building Final | 6/23/2023 | Approved | JEREMY TODD |
| HVAC-Final | 6/23/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 6/23/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Approved | JEREMY TODD |
| Service/Power Release | 6/23/2023 | Approved | JEREMY TODD |
| Smoke Detectors | 6/23/2023 | Approved | JEREMY TODD |
| Final | 6/29/2023 | OK to Issue CofO | JEREMY TODD |